Judgments

Decision Information

Decision Content

A-198-78
Attorney General of Canada (Applicant)
v.
R. S. Tucker (Respondent)
Court of Appeal, Pratte, Urie and Ryan JJ.— Ottawa, September 13 and October 19, 1978.
Judicial review — Public Service — Labour contract — Benefits of overtime clause applicable if work "scheduled overtime" less favourable than benefits under call-back pay clause — Meaning of term "scheduled overtime" — Hand written notice to respondent before end of shift requiring "scheduled overtime" work later that evening — Respondent paid pursuant to overtime clause rather than standby clause — Whether or not P.S.S.R.B. erred in upholding Adjudicator's decision that work performed by respondent not "scheduled overtime" — Public Service Staff Relations Act, R.S.C. 1970, c. P-35, ss. 23, 91 — Federal Court Act, R.S.C. 1970 (2nd Supp.), c. 10, s. 28 — Collective Agreement of April 30, 1969, between the Treasury Board and the Public Service Alliance of Canada with respect to the Clerical and Regulatory Group (All Employees), clauses 27, 30.01.
This is a section 28 application to review and set aside a decision of the Public Service Staff Relations Board on a question of law referred to it and related to the Chief Adjudica tor's interpretation of a clause in the collective agreement between Treasury Board and the Public Service Alliance of Canada with respect to the Clerical and Regulatory Group (All Employees). Respondent, a customs officer whose shift finished at 3:30 p.m., was notified by a hand-written notice attached to his attendance sheet that he was "on scheduled overtime" that evening from 7:55 to 9:00 p.m. and received overtime pay pursuant to Article 27 of the collective agreement. Respondent asserted that he was entitled in the circumstances to standby pay and the appropriate compensation, on the ground that the work performed was not scheduled overtime and referred the matter to adjudication. The Chief Adjudicator found the work was done on a call-back which was not scheduled in advance, entitling the respondent to compensation pursuant to the stand by provision, and the Board found that the Adjudicator did not err in law. The critical question is whether the words "sche- duled in advance" could apply to the work done by respondent.
Held, the application is allowed. The term "scheduled in advance", as used in clause 30.01, imports the sense of reason able advance notice; an employee's recall would be "scheduled in advance" if he had notice of it far enough ahead to make reasonable rearrangements in his own plans. On the other hand, a recall occasioned by a situation of which reasonable advance
notice could not be and was not in fact given would be within the protection of the guarantee given in the standby clause. There is no need, in order to give effective meaning to the disputed words, to make a distinction between a schedule, formal and general in character, applying to more than one employee or to more than one assignment, and an ordinary notice, provided that the employee affected was given reason able advance warning of the extra work. The Public Service Staff Relations Board erred in law to the extent that the Board found that the disputed words in clause 30.01 necessarily referred to a schedule, formal and general in nature, and thus that the words could refer only to a recall under such a schedule.
Re International Molders & Allied Workers Union, Local 49 v. Webster Manufacturing (London) Ltd. (1972) 23 L.A.C. 37, referred to. Attorney General of Canada v. Public Service Staff Relations Board [1976] 2 F.C. 163, referred to.
APPLICATION for judicial review. COUNSEL:
W. L. Nisbet, Q.C. for applicant. M. W. Wright, Q.C. for respondent.
SOLICITORS:
Deputy Attorney General of Canada for applicant.
Soloway, Wright, Houston, Greenberg,
O'Grady, Morin, Ottawa, for respondent.
The following are the reasons for judgment rendered in English by
RYAN J.: This is an application under section 28 of the Federal Court Act to review and set aside a decision made by the Public Service Staff Rela tions Board, dated April 11, 1978. The decision was rendered on a question of law referred to the Board by Her Majesty pursuant to section 23 of the Public Service Staff Relations Act', R.S.C. 1970, c. P-35, which section was in force at the time. Section 23 provided:
23. Where any question of law or jurisdiction arises in connection with a matter that has been referred to the Arbitra tion Tribunal or to an adjudicator pursuant to this Act, the Arbitration Tribunal or adjudicator, as the case may be, or either of the parties may refer the question to the Board for hearing or determination in accordance with any regulations made by the Board in respect thereof, but the referral of any such question to the Board shall not operate to suspend any proceedings in connection with that matter unless the Arbitra-
' Section 23 was repealed by S.C. 1974-75-76, c. 67, s. 11, effective October 11, 1975.
tion Tribunal or adjudicator, as the case may be, determines that the nature of the question warrants a suspension of the proceedings or unless the Board directs the suspension thereof.
The question of law referred to the Board relat ed to the interpretation by Edward B. Joliffe, Q.C., in his capacity as Chief Adjudicator, of a clause in a collective agreement, signed on April 30, 1969, between the Treasury Board and the Public Service Alliance of Canada with respect to the Clerical and Regulatory Group (All Employees). The matter came before the Chief Adjudicator on a reference to adjudication by the respondent, Mr. Tucker, pursuant to section 91 of the Public Service Staff Relations Act e .
The . factual background to Mr. Tucker's griev ance is set out in a written statement which was agreed to by counsel before the Chief Adjudicator:
1. He is a senior customs officer at Edmonton Airport and is a shift worker.
2. On July 24 or 25, 1969, he was notified in writing which notice was attached to his attendance sheet that he was "on scheduled overtime" for July 27 at 8:10 P.M.
3. On July 27, his regularly scheduled working hours were from 7:30 A.M.-3:30 P.M. (8-hour shift with 1 / 2 hour lunch break) and, in accordance with the notice given to him on July 24 or 25, he then proceeded to work that evening from 7:55 to 9:00 P.M. on the so-called pre-scheduled overtime, and received overtime pay pursuant to Art. 27.
After referring to the agreed statement, the Adjudicator, in his reasons for decision, proceeded:
According to the grievance presented by Mr. Tucker on August 12, 1969, his overtime work on July 27 was performed from 7:55 p.m. to 9:00 p.m. at the Edmonton International Airport, and he asserted that he thereby became entitled to standby pay and the appropriate compensation under Article 32 of the collective agreement. The employer's replies to the grievance all alleged that Mr. Tucker had been "scheduled" to report for overtime to be worked at a specific time with respect to Air Canada Flight 853. The reply at the second level
2 Section 91 of the Public Service Staff Relations Act pro vides in part:
91. (1) Where an employee has presented a grievance up to and including the final level in the grievance process with respect to
(a) the interpretation or application in respect of him of a provision of a collective agreement or an arbitral award,
and his grievance has not been dealt with to his satisfaction, he may refer the grievance to adjudication.
specifically stated that the written notification given to Mr. Tucker was on July 25.
A copy of the notice was filed, certified correct by the signatures of counsel. It is simply an undated hand-written memorandum on a plain sheet of paper made with either pen or pencil and reading as follows:
"Scheduled Overtime
July 27
AIR CANADA/853 ETA 8 10 PM R. Tucker"
The Adjudicator held that it was clear that Article 32 of the collective agreement, the "STANDBY" article, was not applicable in this case, and this finding was not in issue.
The critical claim of Mr. Tucker was that he was entitled to "CALL-BACK PAY" under Article 30 of the collective agreement, which reads:
ARTICLE 30 CALL-BACK PAY
30.01 When an employee is recalled to a place of work for a specific duty, and such recall has not been scheduled in advance, he shall be paid the greater of:
(a) compensation equivalent to four (4) hours' pay at his straight-time rate, or
(b) compensation at the applicable overtime rate,
provided that the period of overtime worked by the employee is not contiguous to his scheduled working hours.
30.02 When an employee is recalled to work overtime under the conditions described in Clause 30.01, and is required to use transportation services other than normal public transportation services, he shall be paid, to a maximum of three dollars ($3.00) each way:
(a) mileage allowance at the rate normally paid by the Employer where the employee travels by means of his own automobile, or
(b) out-of-pocket expenses for other means of commercial transportation.
If Mr. Tucker's submissions were well founded, he would be entitled to receive, for work done on the recall, at least four hours' pay at his straight time rate because that would be in excess of what his compensation would be at the applicable over time rate for the time he actually worked. He would, however, not have the right to the guaran teed minimum if his recall had been "scheduled in advance". The critical question then is whether the
words "scheduled in advance" could apply to the work which he did and of which he had received written notice in the manner indicated.
The Adjudicator found that the work Mr. Tucker did was work done on a call-back which had not been scheduled in advance and, according ly, that he was entitled to the four-hours' straight time guarantee. His finding was based on a meticulous analysis of the language of the various clauses in the agreement which related to the scheduling of work, particularly clauses falling within Article 26 (Hours of Work), Article 27 (Overtime), Article 28 (Pay), Article 30 (Call- back Pay) and Article 32 (Standby). As I read his reasons, I concluded that he was of the view, based on his analysis, that the informal one-shot "notice" given to Mr. Tucker could not be a "schedule", and that the work done by Mr. Tucker during the evening of July 27, 1969 could not have been done pursuant to a recall "scheduled in advance" because it was not provided for in a document of some generality and formality, a document apply ing to more than a single assignment.
The question of law referred to the Public Ser vice Staff Relations Board was in these terms:
Whether the Chief Adjudicator erred in law in deciding that the Grievor's claim fell within the ambit of clause 30.01 of the Collective Agreement between Treasury Board and the Public Service Alliance of Canada with respect to the Clerical and Regulatory Group, Code: 503/4/69. More particularly and without limiting the generality of the foregoing, whether the Chief Adjudicator erred in law in making use of articles 26 and 27 of the collective agreement in construing the term "sched- uled in advance" found in clause 30.01 of the agreement.
The Board found':
... the Board is of the opinion that the adjudicator did not err in law when he found the following:
(a) the collective agreement makes no provision for "pre- scheduled overtime"; the fact that the note passed to Mr. Tucker is headed "scheduled overtime" is not significant,
(b) Mr. Tucker had been recalled to work,
(c) the recall had not been scheduled in advance within the meaning of the word "schedule" in the collective agreement. (See paragraph 21 above.)
(d) Mr. Tucker was therefore "entitled to compensation under article 30.01(a), being compensation equivalent to four hours' pay at his straight-time rate."
3 There was a dissenting opinion.
I would note that paragraph 21 of the majority's reasons for decision reads in part:
From this study, the chief adjudicator concludes that the word "schedule" as used in the collective agreement refers to an arrangement of general application and that "there is nothing to suggest an ad hoc or `one-shot' arrangement for one employee with respect to working overtime, with or without notice."
This finding by the chief adjudicator expresses the same con clusion that was reached by adjudicator Perry Meyer in the A. Yvon Paul case (166-2-406) where it is shown that a pattern of work repeated over a period of time, in this case, month by month, constitutes a schedule. In this kind of arrangement, it is possible that a recall be scheduled in advance when an employee is designated as the person who may be called to work overtime during certain specified week-ends. In the case at hand, if the employer had posted a schedule mentioning, for example, that the aggrieved employee could be required to report for work every Wednesday night (or alternate Wednes- day night) outside his regular hours of work to meet a certain flight, this would have constituted a recall scheduled in advance as implied in article 30.01 of the collective agreement. But such is not the case.
The applicant did not dispute that the respond ent had been recalled. The applicant's critical sub mission, as I understood it, was that the disputed words in clause 30.01 were capable of applying to the extra work done by Mr. Tucker in response to the written notice given to him; that a recall "scheduled in advance" could include a recall, by way of a written notice given in advance, of an employee to do a particular job.
That in the circumstances of this case there was a recall seems quite clear even though Mr. Tucker was given the recall notice by means of a note attached to his attendance sheet and thus appears to have known of the recall before he left his place of work. I read Article 30 as applying to a "recall" in the sense of a requirement to return to do a job outside an employee's regularly scheduled hours of work, provided that the job is not done during time immediately contiguous to his regular hours: a "call-back" would not include overtime done by an employee who stays on after his regular shift or returns before and stays on into his next shift. The purpose of clause 30.01 would seem to have been (subject to the exception in dispute) to assure an employee who was required to make an extra trip to his place of work compensation in an amount at least equal to four hours' straight time. This would constitute at least a minimum payment designed to compensate the employee not only for work actual-
ly done, but as well for the personal incon venience resulting from the disturbance of his otherwise free time. Clause 30.02 made provision to cover extra travelling expenses of such a trip. A purpose of the guarantee might also have been to discourage recalls for brief jobs'.
Nonetheless, despite the underlying purposes of the guarantee, the parties did provide for an excep tion to it: it was not to apply if the recall were "scheduled in advance".
The meaning of this qualification is not immedi ately obvious. I can quite understand why the Adjudicator and the Board searched through other clauses of the agreement for assistance in inter preting clause 30.01, and there was, of course, no reason in law why they should not have done so. Quite frankly, however, I do not find a close textual analysis of such terms as "schedule", "notice", and "scheduled", as used within the con text of other clauses serving quite different pur poses, particularly helpful. In fact, I find that this sort of analysis leads to, what appears to me to be, a rather strained reading of the disputed words.
To me the essential reason for excepting from the guarantee recalls "scheduled in advance" appears to have been to distinguish between recalls which could reasonably be foreseen and of which advance notice could and should be given, and those which would not be reasonably foreseeable and thus of which notice could not be given. A justification for the distinction might be found in the fact that a disturbance in an employee's free time might be less disruptive if it were foreseen and could be planned for by him. The term "sched- uled in advance", as it is used in clause 30.01, imports the sense of reasonable advance notice; an employee's recall would be "scheduled in advance" if he had notice of it far enough ahead to make reasonable rearrangements in his own plans, so that he could say of it, quite naturally, that he was scheduled to work at the time indicated, just as he
4 I have found helpful the consideration given to the signifi cance of a "call-back" clause in the majority reasons of the board of arbitration in Re International Molders & Allied Workers Union, Local 49 v. Webster Manufacturing (London) Ltd. (1972) 23 L.A.C. 37.
might say that he was "scheduled" to go to his doctor for a check-up if he had an appointment to do so.
On the other hand, a recall occasioned by an emergency or a recall occasioned by an occur rence, falling short of an emergency, of which reasonable advance notice could not be, or was not in fact, given would be within the protection of the guarantee. It would not be a "recall scheduled in advance". I see no need, nor do I find it very helpful, with respect, in order to give effective meaning to the disputed words, to make a distinc tion between a schedule, formal and general in character, applying to more than one employee or to more than one assignment, and an ordinary notice, provided that the employee affected was given reasonable advance warning of the extra work. Even a recall included in a formal docu ment, general in character, might occasion person al inconvenience and extra expense to those affect ed by it; but the Board's reading of the words in issue would itself have the effect of excluding such a recall, despite its inconvenience and possible expense, from the guarantee.
In my view, the Public Service Staff Relations Board erred in law to the extent the Board found that the disputed words in clause 30.01 necessarily referred to a schedule, formal and general in char acter, and thus that the words could refer only to a recall under such a schedule. I would, therefore, grant the application and set aside the decision of the Board. I would refer the matter back to the Board with a direction that it should answer the question of law referred to it by holding that the Adjudicator erred in law in deciding that Mr. Tucker's claim fell within the ambit of clause 30.01 of the collective agreement to the extent that the Adjudicator's decision involved construing the disputed words as being applicable only to a recall made by way of a schedule of some generality and formality, and thus as not being capable of apply ing to Mr. Tucker's recall.
I would indicate, however, that whether or not a recall is "scheduled in advance" must generally be a question, not of law, but of fact. In this case, for example, once the mistake of law is corrected, it must be for the Adjudicator, and not for the
Board, to decide whether Mr. Tucker's recall had in truth been "scheduled in advance". I would therefore direct the Board to refer the grievance back to adjudication so that the Adjudicator may decide the grievance on the basis that Mr. Tuck er's recall was susceptible of falling within the disputed words of clause 30.01 and thus could be excluded from the guarantee afforded by the clause 5 .
Before concluding, however, I would observe that counsel for the respondent relied on a series of judicial decisions in which it has been held that, where the decision of an arbitrator under a collec tive agreement, based on an interpretation of the agreement, is subject to judicial review, the deci sion will not be disturbed for error of law if the decision was reasonably open to the arbitrator 6 . He submitted that these decisions are applicable in the present case. I would note that counsel for the applicant did not, as I understood him, disagree that the decisions would apply if we were to find that the Board's interpretation was reasonably open to it. This Court made it clear, however, that, having in mind our duties under section 28 of the Federal Court Act, we could not accept a conces sion on this point as being in any way decisive.
Though I, with respect, disagree for the reasons I have given with the Board's interpretation of the disputed words in clause 30.01 of the collective agreement, I did say earlier in these reasons that the meaning of these words was not obvious. It does not, however, follow that the decisions relied on by the respondent are applicable. It would not, indeed, follow that they would be applicable even if it could be said of the Board's interpretation that, though erroneous, it was not unreasonable. So far as this Court is concerned, the present case
5 See Attorney General of Canada v. The Public Service Staff Relations Board [1976] 2 F.C. 163, at pages 167 and 168.
6 See, for example, Re Canadian Westinghouse Co. Ltd. v. Local 164 Draftsmen's Association of Ontario (1962) 30 D.L.R. (2d) 673 (Ont. C.A.); Regina v. Weatherill, Ex parte Falconbridge Nickel Mines Ltd. (1969) 10 D.L.R. (3d) 533 (Ont. C.A.); and Re United Glass and Ceramic Workers of North America (AFL-CIO-CLC), Local 246 v. Dominion Glass Co. Ltd. (1974) 40 D.L.R. (3d) 496 (Ont. C.A.). And see also International Association of Machinists and Aerospace Workers, Flin Flon Lodge No. 1848 v. Hudson Bay Mining and Smelting Co., Limited [1968] S.C.R. 113.
does not involve the review of a decision of an arbitrator or an adjudicator 7 . It involves the review of a decision of the Public Service Staff Relations Board on a question of law referred to it. It was for the Board to decide whether the inter pretation given to the collective agreement by the Adjudicator was correct, not whether it was one that was reasonably open to him. And it is the function of this Court, in reviewing the decision of the Board under section 28 of the Federal Court Act, to determine whether the Board's decision was correct in law.
* * *
PRATTE J. concurred.
* * *
URIE J. concurred.
'I do not, accordingly, find it necessary to decide whether the decisions relied on would be applicable if such a review were involved.
 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.