Judgments

Decision Information

Decision Content

T-665-79
Enconair Systems Ltd. (Plaintiff)
v.
The Queen (Defendant)
Trial Division, Smith D.J.—Winnipeg, February 27 and June 27, 1979.
Crown — Contracts — Plaintiff subcontracted to supply and erect growth chambers in building under construction by another contractor — Expenses allegedly to be borne by the contractor for the building, assumed by the plaintiff Whether or not plaintiff entitled to compensation for these expenses — Alternatively, whether or not an order should issue pursuant to Rule 327 directing the trial of an issue to determine if plaintiff entitled to such declaration — Federal Court Rules 327, 341.
This is a motion under Rule 341 for a judgment declaring that, pursuant to the terms of sections 15 B.5.7 and 15 C.5.7 of a contract, plaintiff is entitled to compensation from the defendant for certain costs and expenses that allegedly were to be assumed by the general contractor but actually were borne by plaintiff, or alternatively, for an order pursuant to Rule 327 directing the trial of an issue to determine whether or not plaintiff is entitled to such declaration. The question of liability depends solely on who is meant by the term "General Contrac tor" in those sections. The contract with which this action is concerned (the second contract) is one under which plaintiff undertook to supply and erect in place plant growth chambers in a building being constructed by Poole Construction Com pany Limited under a contract (the first contract) let by the defendant.
Held, the motion is allowed. The general contractor and the supplier referred to in the paragraphs in question cannot be the same legal entity. In these paragraphs the word "supplier" refers to the plaintiff. The term "General Contractor" as used in these two paragraphs must mean the building general con tractor, who would be in charge of the building site and of the growth building during its construction. In all six places in the contract in which the term "General Contractor" is used, it means the general contractor for the building and not the plaintiff. Although defendant's counsel cited several paragraphs in the specifications to support his submission that the words "General Contractor" should be interpreted as meaning the plaintiff, such an interpretation would not be logical. Certain subsections referred to were general requirements of the con tract and would give way in the event of conflict with specific subsections. Other subsections cited were not applicable to the question before the Court. Plaintiff cannot compel Poole Con struction Company Limited to compensate it for the costs and expenses in question as that company is not a party to the contract. Nevertheless, plaintiff was forced to do itself things which Poole Construction Company Limited was to do pursu ant to plaintiff's contract with the Crown, and so incurred expenses in performing that contract that should have been borne by the company. As it has no redress against that
company, plaintiff is entitled to be compensated by the Crown for those costs and expenses.
MOTION for judgment under Rule 341.
COUNSEL:
John S. Lamont, Q.C. for plaintiff. Sherwin Lyman for defendant.
SOLICITORS:
Aikins, MacAulay & Thorvaldson, Win- nipeg, for plaintiff.
Deputy Attorney General of Canada for defendant.
The following are the reasons for order ren dered in English by
SMITH D.J.: This is a motion, under Rule 341 for a judgment declaring that, pursuant to terms of sections 15 B.5.7 and 15 C.5.7 of the agreement referred to in the statement of claim, the plaintiff is entitled to compensation from the defendant for the costs and expenses referred to in paragraphs numbered 6 and 7 of the statement of claim, or in the alternative, for an order pursuant to Rule 327 directing the trial of an issue to determine whether or not the plaintiff is entitled to such a declaration, or for such further or other order as may be just.
Rule 327 is as follows:
Rule 327. Upon any motion the Court may direct the trial of any issue arising out of the motion, and may give such direc tions with regard to the pre-trial procedure, the conduct of the trial and the disposition of the motion as may seem expedient.
And Rule 341 reads:
Rule 341. A party may, at any stage of a proceeding, apply for judgment in respect of any matter
(a) upon any admission in the pleadings or other documents filed in the Court, or in the examination of another party, or
(b) in respect of which the only evidence consists of docu ments and such affidavits as are necessary to prove the execution or identify of such documents,
without waiting for the determination of any other question between the parties.
The question of liability in this action depends, on the evidence before me, solely on who is meant by the term "General Contractor", as that term is
used in sections 15 B.5.7 and 15 C.5.7 of the specifications forming part of the agreement referred to in the statement of claim, which is an agreement between Her Majesty the Queen, repre sented by the Department of Public Works, and the plaintiff.
There were, in fact, two contracts being carried out at approximately the same time. The first was a building contract let by the defendant, represent ed by the Department of Public Works, to Poole Construction Company Limited, to erect a build ing, sometimes referred to herein as the "growth building", for the Department of Agriculture, at the City of Saskatoon. The second was a contract under which the plaintiff undertook to supply and erect in place, in the building being erected under the first contract, eighteen plant growth chambers of the walk-in type and ten plant growth chambers of the reach-in type. It is the second contract with which this action is concerned.
On the first page of this contract, dated July 8, 1977 the plaintiff is described as "Enconair Sys tems Ltd., a body corporate whose head office or chief place of business is in Winnipeg, Manitoba (referred to in the documents forming the contract as the `Contractor')." The contract is a lengthy one, consisting of five documents, the last of which consists of 64 pages of detailed specifications. Throughout the contract documents the plaintiff is referred to a great many times by the term "Con- tractor". In the specifications it is referred to as the "Contractor" twenty-one times, and is also referred to as the "Manufacturer" eight times and twice as the "Supplier".
Section 15 B of the specifications contains, in nineteen pages, the detailed specifications for the walk-in growth chambers, and section 15 C con tains, in eighteen pages, those for the reach-in growth chambers.
As indicated at the beginning of these reasons the plaintiff is relying primarily on the provisions of section 15 B.5.7 and section 15 C.5.7. Section 15 B.5.7 reads:
15 B.5.7 The General Contractor shall receive the equipment, store safely, move crates to final location, using hoists or winches as required without charge to supplier.
As this paragraph is part of section 15 B it obviously relates to the walk-in growth chambers. Section 15 C.5.7 is in exactly the same terms, and as it is part of section 15 C it obviously relates to the reach-in growth chambers.
The plaintiff submits correctly that the General Contractor and the supplier referred to in each of these two paragraphs cannot be the same legal entity. Unquestionably the things the General Contractor is required by these contracts to do will involve costs, but none of these costs are to be charged to the supplier. It is further clear to me that in these paragraphs the word "supplier" refers to the plaintiff. Reference to sections 15 B.1 and 15 C.1 will suffice to show that this is so. Para graph .3 of section 15 B.1 describes the work which the Contractor, i.e.: the plaintiff, is required to do with respect to the walk-in growth chambers, and paragraph .3 of section 15 C.1 describes the work the plaintiff is required to do with respect to the reach-in growth chambers. Except for minor differences due to the different types of growth chambers the two paragraphs are couched in simi lar words. It is therefore necessary to quote only one of them. Paragraph .3 of section 15 B.1 reads: 15 B.1 ...
.3 The work covered by this section includes, but is not necessarily confined to the following:
.1 Supply and erection in place of fifteen (15) standard height (80" growth height) walk-in growth chambers. Weight of each chamber shall not exceed 4500 lbs.
.2 Supply and erection in place of three (3) extra height (96" growth height) walk-in growth chambers, weight of each chamber shall not exceed 5000 lbs.
.3 Supply and installation of two (2) portable 24 point camless programmers.
.4 Supply and installation of all refrigeration required.
.5 Supply and installation of air cooled condensers on the roof for the walk-in chambers.
.6 This Section shall be responsible for the supply and installation in the correct location of all necessary anchor bolts to securely fasten above air cooled condensers to struc tural steel beams.
.7 Provide rubber in shear insulators under all bolts holding down above Air Cooled Condensers if the motors in the condensers are not resiliently mounted.
Since, by the terms of these seven subpara- graphs the plaintiff is expressly required to supply and erect or to supply and install everything called
for by the contract, the word "supplier" in sections 15 B.5.7 and 15 C.5.7 must mean the plaintiff.
To my mind it is also clear that the term "General Contractor" as used in those two para graphs must mean the Building General Contrac tor, who would be in charge of the building site and of the growth building during its construction, and would therefore be the proper party to receive and store, pending installation, equipment deliv ered to the site by the plaintiff under its contract.
Sections 15 B.5 and 15 C.5 contain other provi sions which confirm the foregoing conclusion. These sections are respectively concerned with erection and installation of the walk-in growth chambers and the reach-in growth chambers. Paragraph .3 of section 15 B.5 provides (that the Contractor shall):
.3 Ensure sufficient pre-delivery notification to co-ordinate with the Building General Contractor all scheduling of installation.
When, four short paragraphs later, paragraph .7 of section 15 B.5 says "The General Contractor shall receive the equipment, store safely, etc.", I cannot think that the term "General Contractor" means anyone other than the Building General Contractor with whom "all scheduling of installa tion" is to be co-ordinated. The final "clincher" is found in paragraph .3 of section 15 C.5, which corresponds, with respect to reach-in growth chambers, with what paragraph .3 of section 15 B.5 says with respect to walk-in growth chambers. Paragraph .3 of section 15 C.5 is in the same words as paragraph .3 of section 15 B.5 with the significant difference that instead of directing the Contractor (plaintiff) to co-ordinate scheduling of installation with the Building General Contractor it directs such scheduling to be co-ordinated with the General Contractor. As the two paragraphs are concerned with precisely the same duty of the Contractor it is clear that the terms "Building General Contractor" and "General Contractor" have the same meaning. There is no basis for thinking otherwise.
The only place throughout all the contract docu ments in which the term "Building General Con-
tractor" is found is in paragraph .3 of section 15 B.5 of the specifications (supra). The term "Gen- eral Contractor" is found in three places in addi tion to the three mentioned supra, viz. in subsec tions .20 and .21 of section 1 A of the specifications, which section sets out the general requirements of the contract, and in subsection .17 of section 15 A of the specifications, which section contains the general clauses and conditions appli cable to the mechanical work of the contract specifications.
Subsection .20 of section 1 A begins:
The General Contractor shall provide and maintain access and operating space for the erection equipment of any contractor.
Surely, in this context, the words "General Con tractor" must mean the Building General Contrac tor and the words "any contractor" must refer to contractors like the plaintiff. This conclusion is made more certain by subsection .21, which, in two paragraphs, directs that the contractor (plain- tiff) shall:
.1 Co-ordinate the work of this- specification with the construc tion of the Growth Building.
.2 Provide two (2) weeks advance notification of all deliveries to the building site to the General Contractor for the building.
Finally, paragraph .2 of subsection .17 of section 15 A directs the contractor, in its first sentence to:
.2 Arrange with the General Contractor all sleeves and opening sizes and location and make provision, if necessary, so as to ensure such are suitable for all equipment.
Here again it is obvious that the term "General Contractor" means the General Contractor for the building. Thus, in my opinion, in all six places in the contract in which the term "General Contrac tor" is used, it clearly means the General Contrac tor for the building, and not the plaintiff.
Counsel for the defendant submitted that in sections 15 B.5.7 and 15 C.5.7 the words "General Contractor" should, or at least could, be interpret ed as meaning the plaintiff. As indicated above I do not agree that such an interpretation would be in any way logical. However, counsel cited several paragraphs in the specifications in support of his
submission and I deem it desirable to consider them.
1. Subsections .1, .2 and .3 of section 1 A.10 of the specifications. This section is found among the general requirements of the contract specifications. The subsections require the contractor (plaintiff) to:
.1 Deliver, store and maintain packaged materials with manufacturer's seals and labels intact.
.2 Prevent damage, adulteration and soiling of materials during delivery, handling and storage. Immediately remove rejected materials from site.
.3 Store materials in accordance with suppliers' instructions.
To begin with there are a few observations that should be made with respect to these subsections. Subsection .1 refers only to packaged materials purchased from or supplied by manufacturers. From other provisions of the contract it is clear that the requirement that the manufacturer's seals and labels be kept intact is designed to ensure that the engineer or other owner's representative can determine that the packaged items have been made by competent reliable manufacturers. The only relevance subsection .2's requirement to "immediately remove rejected materials from site" has to the issue of who is meant by the term "General Contractor" is that it is the only place in section 1 A.10 where the site is specifically referred to. In subsection .3 it is obvious that the word "suppliers" refers to the manufacturers.
It must be remembered that these subsections are general requirements of the contract. If there is a conflict between what is provided in them and the subsequent specific provisions in sections 15 B.5.7 and 15 C.5.7 the specific provisions must prevail. It may be that sections 15 B.5.7 and 15 C.5.7 are intended to be read together with subsec tions .1, .2 and .3 of section 1 A.10 as meaning that for the period between the delivery of ma terials to the site and their use in erecting and installation of the growth chambers, the obliga tions imposed on the plaintiff by the said subsec tions to keep the manufacturer's seals and labels
intact, to store the materials in accordance with the manufacturer's instructions and to prevent damage, adulteration and soiling thereof, are transferred to the General Contractor. As the building contract between Her Majesty and Poole Construction Company Limited is not before the Court on this motion we do not know whether that contract contains any provision to the same effect.
2. Section 15 A.9.6.
Section 15 A.9 contains seven paragraphs of general clauses setting out the liability of the contractor (plaintiff) in connection with the mechanical work of the contract. Subsection .6 reads:
.6 Assume responsibility for the condition of all material and equipment supplied under this section and provide all necessary protection for same.
What I have said with respect to subsections .1, .2 and .3 of section 1 A.10 applies equally to this subsection.
3. Section 15 A.20.
This is another section of the general clauses concerning the mechanical work of the contract. Subsection .1 reads, in part:
.1 Protect all equipment during and after installations ....
This subsection relates to the period "during and after installation". Sections 15 B.5.7 and 15 C.5.7 relate to the period prior to installation. This subsection .1 of section 15 A.20 has no relevance to the question we are concerned with.
4. Subsection .5 of Section 15 A.25.
Counsel gave considerable emphasis to this sub section, which reads:
.5 Where there are two or more interpretations that can be taken from the specifications or the drawings in regard to materials, equipment or layout and clarification is not obtained from the Engineer, then this Contractor shall consider the most costly of the alternatives to apply in his tender and no allow ances will be made or considered if his estimate and tender have been based on the lesser.
In my view it can be argued that this subsection applies only to what is said in the specifications and portrayed in the drawings about what ma terials and equipment are to be used and what the layout shall be, and does not apply to services like
the movement or storage of materials and equip ment. Even if this argument is not entitled to succeed, the subsection cannot be held to defeat the plaintiff's claim, because in my opinion there is only one meaning that can logically be accorded to the term "General Contractor" as that term is used in sections 15 B.5.7 and 15 C.5.7 of the specifications, i.e.: that it means the General Con tractor that is to construct the growth building under the first contract, viz. Poole Construction Company Limited. Therefore the subsection is not applicable to the question before the Court on this motion.
The plaintiff is entitled to a declaratory judg ment that it is entitled to compensation from the defendant, pursuant to sections 15 B.5.7 and 15 C.5.7 of the specifications forming part of the agreement between the parties, for the costs and expenses incurred by the plaintiff by reason of the refusal of Poole Construction Company Limited to receive at the site the plant growth chambers, together with incidental equipment and materials, to store the same safely and to move crates con taining the same to final location, all of which were to be done by Poole Construction Company Limited, without charge to the plaintiff. The plain tiff relied on the said sections 15 B.5.7 and 15 C.5.7 in making its tender. As Poole Construction Company Limited is not a party to the contract between the plaintiff and the defendant, the plain tiff cannot compel that company to compensate it for the costs and expenses in question. The defend ant has not required the company to compensate the plaintiff for the costs in question. There may be no provision in the contract between Her Majesty and the company that obligates the com pany to do the things, the failure of the company to do which has occasioned the costs and expenses for which the plaintiff is seeking compensation. Be that as it may, the plaintiff, having been forced to do itself the things which the company was to do pursuant to sections 15 B.5.7 and 15 C.5.7 of the plaintiff's contract with Her Majesty and by so doing having incurred costs and expenses in per forming that contract which by the contract should have been borne by the company, and having no redress against the company, is entitled to be compensated by Her Majesty for those costs and expenses.
The amount of the costs and expenses cannot be dealt with on this motion. There will therefore be an order directing an issue between the parties to determine the amount of compensation to be paid by the defendant to the plaintiff.
The plaintiff is entitled to the costs of this motion.
 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.