Judgments

Decision Information

Decision Content

A-472-87
In the matter of the National Energy Board Act
And in the matter of a reference by the National Energy Board pursuant to subsection 28(4) of the Federal Court Act
INDEXED AS: NATIONAL ENERGY BOARD (RE)
Court of Appeal, Mahoney, Stone and MacGuigan JJ.—Toronto, November 4 and 5; Ottawa, November 27, 1987.
Constitutional law — Distribution of powers — National Energy Board authorizing construction of proposed bypass pipeline from TransCanada PipeLines' metering station direct ly to end-user's plant — Board lacking jurisdiction — Erred in drawing analogy between broadcasting systems and pipe lines — Not interprovincial "work" as pipeline entirely within Province — CCPI not operating interprovincial undertaking as bypass pipeline not necessary to operation of whole — Consti tution Act, s. 92(10)(a) requiring interprovincial undertaking of transportation or communications nature — Necessary nexus test applied — Proposed pipeline not necessary to interprovincial undertaking of TCPL.
Energy — National Energy Board ordering reference to Federal Court to determine whether proposed bypass pipeline within federal legislative competence, hence within Board's jurisdiction — Board authorizing construction of pipeline — Ontario Energy Board holding it had jurisdiction over bypass lines within Province — Ontario Divisional Court upholding provincial jurisdiction over such pipelines — Court decision constituting change of circumstances raising doubt as to cor rectness of Board's decision — Irrelevant who brings changed circumstances to Board's attention as able of own motion to initiate review of any of its decisions — Board lacking juris diction as proposed pipeline not interprovincial "work" or undertaking.
This was a reference by the National Energy Board (NEB) to determine whether a proposed bypass pipeline came under the Board's jurisdiction as being within Parliament's legislative authority. Prior to March 1986, "Cyanamid" purchased gas from "Consumers' ", which in turn purchased gas from Trans- Canada PipeLines Limited ("TCPL"). Subsequently, "CCPI" was incorporated to build and operate a 6.2 km pipeline from TCPL's meter station directly to Cyanamid's plant, bypassing Consumers' pipeline. The NEB authorized the proposed facili ty, but shortly thereafter the Ontario Energy Board (OEB) held that the Province had jurisdiction over bypass pipelines in
Ontario (whereby an end-user of natural gas avoids using the local distribution company by tapping directly into the TCPL system). The Divisional Court upheld that decision. All appeals to this Court against the NEB decision were then withdrawn leaving CCPI with unchallenged NEB orders in its favour, but subject to possible penalties in Ontario if it proceeded to implement these orders. CCPI therefore sought from the NEB a review of the Board's decision through which a reference might be directed to this Court. The Board held that the operational integration of the enterprises was not sufficient to consider the two pipelines as one, indivisible pipeline system. Neither party's operation was under the care, control or direc tion of the other. However, relying on the Supreme Court of Canada decisions in Luscar, Capital Cities and Dionne, the Board held that the proposed pipeline, although located entirely in the Province, would form a link in a chain for the interpro- vincial transmission of gas.
Held, the proposed pipeline was not within the NEB's jurisdiction.
A preliminary issue of whether the Board had jurisdiction to order the reference was raised. It is well established that the determination of any question so referred must be required to deal with the matter that is before the tribunal making the reference, and not with a merely academic matter. In ordering the reference the Board correctly held that the Divisional Court's decision, which had the effect of nullifying the Board's orders with respect to the CCPI application, was a sufficient change in circumstances to "raise a doubt" regarding the correctness of the previous orders. The Board was also correct in holding that it did not matter that it was the successful party (CCPI) which brought the altered circumstances to the Board's attention, as the Board had the power to initiate of its own motion, a review of any of its decisions.
On the constitutional question, the Board erred in relying so heavily on the cable-television cases. When the Board saw a close analogy between the purpose served by transmission cables and the proposed pipeline, it should have been compar ing broadcasting transmission and pipelines. The Supreme Court of Canada has made it clear that cable transmission was under federal jurisdiction because it was part of a single undertaking (broadcasting), which had already been deter mined to be within federal competence. If one compares natural gas systems and broadcasting systems, there are few similari ties. Radio waves are not confined in space, as gas is confined in a pipeline, and so bear no relationship to territorial bound aries. Their reception is virtually instantaneous. Also, the necessity for allocating space, in the frequency spectrum sug gests the need to regulate both the interprovincial and intrapro-
vincial broadcaster. The broadcasting analogy was inappropri ate for natural gas pipelines.
The Board also erred in relying on the Luscar decision, because there a railway line constructed and owned by an intra- provincial company was operated by C.N., an interprovincial company. No similar agreement whereby TCPL would operate the proposed pipeline existed here.
In order for a work or undertaking to fall under federal jurisdiction under paragraph 92(10)(a) of the Constitution Act, 1867, it must either be an interprovincial work or undertaking or be joined to an interprovincial work or undertaking through a necessary nexus. In the Luscar case, the necessary nexus making the branch line a link in the interprovincial chain was the operating agreement. In the cable-television cases, the necessary nexus was the inseparability of the medium and the message. The only authority which resisted the necessary nexus approach was the Winner case, and there the Privy Council limited its holding to the exact facts. The suggestion that there was a "purpose/nature of the undertaking test" whereby juris diction was attributed on the basis of the overall purpose of an enterprise was limited to cases where there was a single busi ness undertaking. Failing an application by TCPL to build and operate the bypass pipeline as its own, the necessary nexus test must be met to establish federal jurisdiction under paragraph 92(10)(a).
As the proposed pipeline would be solely within Ontario, it cannot be an interprovincial "work" (defined as "physical things, not services"). Mere physical connection to an interpro- vincial work is not sufficient to found federal jurisdiction.
The bypass pipeline was not part of an interprovincial under taking by CCPI because it was not necessary to the operation of the whole. Even if CCPI could be considered to be engaged in an interprovincial undertaking, it would not be of a transpor tation or communications character such as is required for federal jurisdiction under paragraph 92(10)(a). Although TCPL operated an interprovincial undertaking, the proposed pipeline was not integral or necessary to TCPL's interprovincial transmission of natural gas. The proposed pipeline offered no advantage to TCPL, but served as one end-user's link with the main line.
STATUTES AND REGULATIONS JUDICIALLY CONSIDERED
Constitution Act, 1867, 30 & 31 Vict., c. 3 (U.K.) [R.S.C. 1970, Appendix II, No. 5] (as am. by Canada Act 1982, 1982, c. 11 (U.K.), Schedule to the Consti tution Act, 1982, Item 1), ss. 91(2),(29), 92(10)(a).
/Draft] NEB Rules of Practice and Procedure, R. 41.
Federal Court Act, R.S.C. 1970 (2nd Supp.), c. 10, s. 28(4).
National Energy Board Act, R.S.C. 1970, c. N-6, ss.
17(1), 49 (as am. by S.C. 1980-81-82-83, c. 116, s. 15), 59(3) (as am. idem, s. 17).
CASES JUDICIALLY CONSIDERED
APPLIED:
British Columbia Electric Ry. Co. Ltd. et al. v. Canadian National Ry. Co. et al., [1932] S.C.R. 161; Cannet Freight Cartage Ltd. (In re), [1976] 1 F.C. 174; (1976), 11 N.R. 606; (1975), 60 D.L.R. (3d) 473 (C.A.); Mon- treal City v. Montreal Street Railway Company, [1912] A.C. 333 (P.C.); In re Regulation and Control of Radio Communication in Canada, [1932] A.C. 304 (P.C.); Re The Queen and Cottrell Forwarding Co. Ltd. (1981), 33 O.R. (2d) 486; 124 D.L.R. (3d) 674 (Div. Ct.).
DISTINGUISHED:
Luscar Collieries v. McDonald, [1927] A.C. 925 (P.C.); Attorney-General for Ontario v. Israel Winner, [1954] A.C. 541 (P.C.); Capital Cities Communications Inc. et al. v. Canadian Radio-Television Commn., [1978] 2 S.C.R. 141; (1978), 18 N.R. 181; (1977), 81 D.L.R. (3d) 609; Public Service Board et al. v. Dionne et al., [1978] 2 S.C.R. 191; (1978), 18 N.R. 271.
CONSIDERED:
Dome Petroleum Ltd. v. National Energy Board (1987), 73 N.R. 135 (F.C.A.).
REFERRED TO:
Public Service Staff Relations Act (Reference re), [ 1973] F.C. 604 (C.A.); Martin Service Station Ltd. v. Minister of National Revenue, [1974] F.C. 398 (C.A.); Alberta Government Telephones v. Canadian Radio-television and Telecommunications Commission, [1985] 2 F.C. 472; (1984), 17 Admin.L.R. 149 (T.D.); revd [1986] 2 F.C. 179; (1985), 17 Admin.L.R. 190 (C.A.); Reference re Industrial Relations and Disputes Act, [1955] S.C.R. 529; Letter Carrier's [sic] Union of Canada v. Canadian Union of Postal Workers et al., [1975] 1 S.C.R. 178; Canadian National Railway Co. v. Nor-Min Supplies Ltd., [1977] I S.C.R. 322; Construction Montcalm Inc. v. Minimum Wage Commission, [1979] 1 S.C.R. 754; Northern Telecom Ltd. v. Communications Workers of Canada, (#1), [1980] 1 S.C.R. 115; (#2), [1983] 1 S.C.R. 733; Toronto Corporation v. Bell Telephone Company of Canada, [1905] A.C. 52 (P.C.).
AUTHORS CITED:
Hogg, Peter W. Constitutional Law of Canada, 2nd ed. Toronto: The Carswell Company Limited, 1985.
COUNSEL:
H. Soudek and Sandra K. Fraser for Nation al Energy Board.
C. Kemm Yates and D. E. Crowther for Cyanamid Canada Pipeline Inc.
Barbara A. Mcisaac for Attorney General of Canada.
Michael M. Peterson and M. P. Tunley for C.I.L. Inc.
Martin Sclisizzi and E. M. Roher for Suncor Inc.
D. O. Sabey, Q.C. for Simplot Chemical
Company Ltd.
Richard Claus van Banning for Nitrochem
Inc.
J. H. Farrell and M. S. F. Watson for Con
sumers' Gas.
B. H. Kellock, Q.C. for Union Gas.
D. S. Morritt for I.C.G. Utilities.
B. Wright and M. Helie for Attorney General
of Ontario.
Barbara C. Howell for Attorney General of
Alberta.
No one appearing for Attorney General of
British Columbia.
N. D. Shende, Q.C. for Attorney General of
Manitoba.
No one appearing for Attorney General for
Saskatchewan.
Louis Crete and Ann M. Bigue for Gaz
Métropolitain.
T. John Hopwood, Q.C. for Novacorp.
D. M. Masuhara for Inland Natural Gas.
Stephen T. Goudge, Q.C. for Ontario Energy
Board.
SOLICITORS:
Legal Services, National Energy Board, Ottawa, for National Energy Board.
Fenerty, Robertson, Fraser & Hatch, Cal- gary, for Cyanamid Canada Pipeline Inc. Deputy Attorney General of Canada for Attorney General of Canada.
Tilley, Carson & Findlay, Toronto, for C.I.L. Inc.
Tilley, Carson & Findlay, Toronto, for Suncor Inc.
Bennett Jones, Calgary, for Simplot Chemical Company Ltd.
Tory, Tory, DesLauriers & Binnington, Toronto, for Nitrochem Inc.
Smith, Lyons, Torrance, Stevenson & Mayer, Toronto, for Consumers' Gas.
Blake, Cassels & Graydon, Toronto, for Union Gas.
Osler, Hoskin & Harcourt, Toronto, for I.C.G. Utilities.
Ministry of Attorney General, Toronto, for Attorney General of Ontario.
Field & Field, Edmonton, for Attorney Gen eral of Alberta.
Ministry of Attorney General, Legal Services Branch, Victoria, for Attorney General of British Columbia.
Legal Services, Winnipeg, for Attorney Gen eral of Manitoba.
Legal Services, Regina, for Attorney General of Saskatchewan.
Clarkson, Tétrault, Montréal, for Gaz Mét- ropolitain.
Howard, Mackie, Calgary, for Novacorp. Legal Services, Inland Natural Gas, Vancou- ver, for Inland Natural Gas.
Gowling & Henderson, Toronto, for Ontario Energy Board.
The following are the reasons for judgment rendered in English by
MACGUIGAN J.: This is a reference by the National Energy Board ("the NEB" or "the Board") under subsection 28(4) of the Federal Court Act [R.S.C. (2nd Supp.), c. 10]. The ques tion referred is as follows:
Are the pipeline facilities proposed to be constructed and operated by Cyanamid Canada Pipeline Inc. within the juris diction of the National Energy Board as being within the legislative authority of the Parliament of Canada pursuant to the Constitution Act, 1867?
I
Cyanamid Canada Inc. ("Cyanamid") operates a manufacturing plant for nitrogen fertilizer prod ucts near Welland, Ontario, which utilizes natural gas as feedstock and as fuel. Prior to March 1986, Cyanamid purchased its total gas requirement from Consumers' Gas Company Ltd. ("Consum- ers' "), which in turn purchased system gas from TransCanada PipeLines Limited ("TCPL").
However by the "Western Accord" of March 28, 1985, the Governments of Canada, Alberta,
British Columbia and Saskatchewan agreed on a more market-oriented domestic pricing regime for natural gas, an initiative which was further devel oped by the so-called "Hallowe'en Agreement" of October 31, 1985.
To take advantage of the new arrangements, Cyanamid incorporated Cyanamid Canada Pipe line Inc. ("CCPI") as a federally-incorporated corporation in 1985. By application dated October 3, 1985, CCPI applied to the NEB for, inter alia, an order of the Board under section 49 of the National Energy Board Act [R.S.C. 1970, c. N-6 (as am. by S.C. 1980-81-82-83, c. 116, s. 15)] ("the Act") authorizing the construction and oper ation of a 6.2 km pipeline for the transmission of gas from the Welland plant site of Cyanamid to the Black Horse Meter Station site of TCPL and an order under subsection 59(3) [as am. idem., s. 17] of the Act directing TCPL to construct inter connecting facilities between the TCPL pipeline system and the applicant's proposed new pipeline at the Black Horse Station. CCPI's proposed pipe line would have the effect of bypassing Consumers' existing pipeline from the Black Horse Station to the Welland plant which presently supplies Cyana- mid and a score of other customers, with cost savings for Cyanamid. After holding public hear ings the Board granted both requested orders in December 1986 (Order No. XG-13-86 and Order No. MO-63-86 respectively).
In the interim period Cyanamid had entered into a gas purchase agreement with a gas producer in Alberta, had applied for and received an Alber- ta Energy Removal Permit, had received interim regulatory approval for transmission of that gas on the TCPL and Consumers' systems, and gas flow had commenced in March 1986. Cyanamid had originally intended that all of these arrangements should be made on its behalf by CCPI, but Con sumers' insisted that it would deal only with Cyanamid itself. Cyanamid still proposes, how ever, to assign the gas purchase agreement to
CCPI, with the Alberta Energy Removal Permit to be re-issued in the name of CCPI.
A nomination procedure would be used by CCPI for the purchase of gas. CCPI would nominate, as frequently as daily (by mid-afternoon for the next morning) the volume of gas required by its Wel- land plant. Nominations would be telecopied both to the Alberta gas producer and to TCPL, and if accepted by both, would be delivered by the pro ducers to the TCPL system at Empress, Alberta, and to CCPI at the Black Horse Station. Delivery would be made on a next-day basis despite the fact that the actual flow-through time for gas from Empress to Welland is several days. Gas delivered by TCPL to CCPI would be metered at the Black Horse Station, and again at the point of sale by CCPI to Cyanamid. Although TCPL would retain the right to isolate the CCPI pipeline from the TCPL system in special circumstances by closing the manually operated valves which connect the two pipelines, CCPI would normally control the flow of gas into its line.
Soon after CCPI's initial application to the NEB, the Ontario Energy Board (the "OEB") called hearings on its own motion to enquire into the issue of bypass, which it defined as the means by which an end-user of natural gas in Ontario, such as Cyanamid, avoids using the local distribu tion company ("LDC"), such as Consumers', by tapping directly into the TCPL system. On December 10, 1986, the OEB held that the prov ince of Ontario, with the OEB as its delegate, has jurisdiction over bypass lines in Ontario, and stated a case to the Divisional Court of the Supreme Court of Ontario to confirm the OEB's jurisdiction with respect to bypass. The Divisional Court in a decision dated March 26, 1987, (Action No. 1243-86) upheld provincial jurisdiction with respect to the typical bypass which inter alia is located entirely within the province and is owned,
controlled, maintained, and operated separately from the interprovincial work to which it is linked.
Following this decision of the Divisional Court, all the applications for leave to appeal which had been lodged with this Court by LDC's against the NEB decision were withdrawn, leaving CCPI with unchallenged NEB orders in its favour, but never theless subject to possible penalties in the province of Ontario if it proceeded to implement these NEB orders. CCPI therefore sought from the NEB under subsection 17 (1) of the Act a review of the Board's decision through which a reference might be directed to this Court under subsection 28(4) of the Federal Court Act. This order of reference was granted by the Board on June 11, 1987.
In the meantime the Lieutenant Governor of Ontario, by Order in Council O.C. 1079/87, dated April 30, 1987, referred the question of provincial legislative jurisdiction over typical bypass pipelines for hearing and consideration by the Ontario Court of Appeal. We were informed during argu ment that the matter had already been argued before that Court and reserved for its decision.
II
A preliminary issue was raised by several parties as to the jurisdiction of the NEB to make this order of reference.
The relevant part of subsection 28(4) of the Federal Court Act reads as follows:
28....
(4) A federal board ... may at any stage of its proceedings refer any question or issue of law, of jurisdiction or of practice and procedure to the Court of Appeal for hearing and determination.
This Court has held that the determination of any question so referred must be required "for the purpose of dealing with the matter that is before the tribunal making the reference and does not contemplate determination of a question of law expressed in academic terms": Public Service Staff Relations Act (Reference re), [1973] F.C. 604 (C.A.), at page 615; Martin Service Station Ltd. v. Minister of National Revenue, [1974] F.C. 398 (C.A.), at page 400. It was argued that, since there was no proceeding pending before the NEB
when the review application was made by CCPI, it could not as the successful party seek a review without running afoul of this rule against general ized and speculative references.
Subsection 17 (1) of the Act, under which CCPI sought and the Board granted the review reads as follows:
17. (1) Subject to subsection (2), the Board may review, rescind, change, alter or vary any order or decision made by it, or may re-hear any application before deciding it.
Subsection (2) has no application in the instant case.
Section 41 of the [Draft] NEB Rules of Prac tice and Procedure, is as follows:
PART V
APPLICATIONS FOR REVIEW OR REHEARING
Applications
41. (1) An application for review or rehearing pursuant to subsection 17(1) of the Act shall be filed in writing with the Secretary.
(2) An application pursuant to subsection (I) shall contain a clear and concise statement of the facts, the nature of the order or decision applied for, and the grounds that the applicant considers sufficient
(a) in the case of an application for review, to raise a doubt as to the correctness of the order or decision including
(i) any error of law or jurisdiction;
(ii) changed circumstances that have arisen since the issu ance of the order or decision;
(iii) new facts that have arisen since the issuance of the order or decision; and
(iv) facts that were not placed in evidence in the original proceeding and that were not discoverable by reasonable diligence; and
(b) in the case of an application for rehearing, to justify a rehearing including
(i) any error of law or jurisdiction;
(ii) changed circumstances that have arisen since the original proceeding;
(iii) new facts that have arisen since the original proceed ing; and
(iv) facts that were not placed in evidence in the original proceeding and that were not discoverable by reasonable diligence.
(3) The applicant shall serve a copy of his application on every person who was a party to the original proceeding.
In the Board's reasons for decision of May 29, 1987, for its Order No. MO-15-87 of June 11, 1987, it resolved this issue as follows (at pages 4-5):
Section 17 of the Act does not limit the right of review to parties who are aggrieved by a decision of the Board; neither does that section restrict a party applying for a review to requesting that the decision be changed. In point of fact, the Act is silent with respect to these matters. In the Board's view subsection 17(1) of the Act gives it the unfettered discretion to review, rescind, change, alter or vary any order or decision made by it. No caveats are attached to this wide power of review. The Board does not agree with the submission that a review where no change is sought is in effect a re-hearing ....
It is the Board's view that CCPI has met the test set out in Rule 41. A Court of competent jurisdiction has ruled that "typical" bypasses within Ontario are within the exclusive jurisdiction of the OEB. In the Board's view this decision of the Ontario Divisional Court amounts to changed circumstances that have arisen since the Board issued its jurisdictional deci sion and this change in circumstances raises a doubt as to the correctness of the Board's decision that it had jurisdiction over the applied-for facilities. In this regard the Board notes the positions taken by certain parties who filed and subsequently withdrew applications to the Federal Court for Leave to Appeal the Cyanamid decision. Statements made by these parties in their letters addressed to the Administrator of the Federal Court of Canada accompanying their Notices of Withdrawal indicate that in the view of these parties, the stated case decision is applicable to the jurisdictional issue which was before this Board in GH-3-86. If these parties are correct then the Board's jurisdictional decision is incorrect.
The fact that the developments, which post-date the Board's jurisdictional decision, and which now cast doubt on that decision have been formally brought to the notice of this Board by a party who does not question the correctness of the Board's original decision on jurisdiction does not, in the Board's view, rob the Board of its jurisdiction to review. It should be noted that the Board has the power, pursuant to section 17, to initiate, of its own motion, a review of any decision made by it.
For all the reasons above-enumerated, the Board has decided to grant the request by CCPI to review the decision on jurisdic tion contained in the Cyanamid decision.
In my view, the Board was entirely within its jurisdiction in holding as it did. It has jurisdiction to review on its own motion, which is not subject to the requirements of section 41 of its Rules. But even on the basis of these requirements, the deci sion by the Divisional Court nullifying by implica tion the Board's orders with respect to the CCPI application was certainly a sufficient change in
circumstances as to "raise a doubt" regarding the correctness of its previous orders.
III
The NEB found it unnecessary to decide the ques tion of constitutional jurisdiction on the basis of the trade and commerce power (subsection 91(2) of the Constitution Act, 1867 [30 & 31 Vict., c. 3 (U.K.) [R.S.C. 1970, Appendix II, No. 5] (as am. by Canada Act 1982, 1982, c. 11 (U.K.), Schedule to the Constitutional Act, 1982, Item 1)]), and, as no party relied on that power in argument before this Court, it will therefore be necessary to consid er the issue only in the light of subsection 91(29) and paragraph 92(10)(a) of the Constitution Act, 1867.
Paragraph 92(10)(a) is as follows:
92. In each Province the Legislature may exclusively make Laws in relation to Matters coming within the Classes of Subjects next herein-after enumerated; that is to say,—
10. Local Works and Undertakings other than such as are of the following Classes: —
(a) Lines of Steam or other Ships, Railways, Canals, Telegraphs, and other Works and Undertakings connect ing the Province with any other or others of the Provinces, or extending beyond the Limits of the Province;
This paragraph must be read in relation with subsection 91(29), which claims for the Federal Parliament such express exceptions from provin cial powers under section 92:
91. It shall be lawful for the Queen, by and with the Advice and Consent of the Senate and House of Commons, to make Laws for the Peace, Order, and good Government of Canada, in relation to all Matters not coming within the Classes of Subjects by this Act assigned exclusively to the Legislatures of the Provinces; and for greater Certainty, but not so as to restrict the Generality of the foregoing Terms of this Section, it is hereby declared that (notwithstanding anything in this Act) the exclusive Legislative Authority of the Parliament of Canada extends to all Matters coming within the Classes of Subjects next herein-after enumerated; that is to say,-
29. Such Classes of Subjects as are expressly excepted in the Enumeration of the Classes of Subjects by this Act assigned exclusively to the Legislatures of the Provinces.
The Board regarded the two principal jurisdic tional questions before it as follows (reasons for decision of December 1986 on Board Orders XG-13-86 and MO-63-86, at page 5):
Do the proposed facilities come within the legislative authority of the parliament of Canada pursuant to the Constitution Act, 1867 (or the British North America Act as it then was)?
If jurisdiction lies with the Government of Canada, do such facilities constitute a "pipeline" as that word is defined in Section 2 of the NEB Act?
Only the first of these jurisdictional questions is constitutional in nature.
With respect to the constitutional question the Board was of the view that it should be stated as follows (decisions, ibid., at page 16):
It is the Board's view that, if jurisdiction in respect of the proposed facilities does lie with Parliament and with this Board, it is because the CCPI pipeline is an integral part of an interprovincial undertaking.
The Board approached this question under the so-called "purpose" and "link-in-the-chain" categories, but distinguished the "vital, essential or integral to the undertaking" test. It relied on the following cases: Luscar Collieries v. McDonald, [1927] A.C. 925 (P.C.); Attorney-General for Ontario v. Israel Winner, [1954] A.C. 541 (P.C.); Capital Cities Communications Inc. et al. v. Canadian Radio-Television Commn., [1978] 2 S.C.R. 141; (1978), 18 N.R. 181; (1977), 81 D.L.R. (3d) 609; Public Service Board et al. v. Dionne et al., [1978] 2 S.C.R. 191; (1978), 18 N.R. 271; Alberta Government Telephones v. Canadian Radio-television and Telecommunica tions Commission, [1985] 2 F.C. 472; (1984), 17 Admin.L.R. 149 (T.D.); revd [1986] 2 F.C. 179; (1985), 17 Admin.L.R. 190 (C.A.).
The Board decided that the operational integra tion of the enterprises is not sufficient to found federal jurisdiction, but that their functional inte gration is (reasons for decision, ibid., at pages 18-21, footnotes omitted):
The Board is not convinced that the degree of operational integration which will exist between CCPI and TCPL is suffi-
cient to consider the two pipelines as one, indivisible pipeline system. CCPI's operation would not be under the care, control or direction of TCPL; the converse is also true. The CCPI facilities would not significantly affect the operation of the TCPL line. Operational integration must, in the Board's view, involve more than mere cooperation and agreement with respect to daily deliveries of gas. In this regard, the Board notes the excerpt from an article entitled "The Federal Case", which was referred to by CCPI's counsel during his final argument. That article noted that there are vital differences between the features of railways and pipelines because, in the case of pipelines, once there is a physical connection, coordinated management and control follow as a matter of course. No doubt, counsel for CCPI intended this article to support his submission that the centralized and coordinated operations, common to any system of interconnecting pipelines, is indica tive, in this case, of the high degree of operational integration which will be required as between TCPL and the proposed CCPI facilities. In the Board's view, the very nature of gas transmission facilities dictates that there be cooperation and coordination between interconnecting lines. This, in and of itself, is not determinative.
5.3.5. Functional Integration
It appears to the Board that the characterization of an undertaking involves answering a fundamental question: what is the undertaking which is in fact being carried on; is there one undertaking or are there two? This question has been posed, in one form or another, in many of the cases which involved the characterization of an undertaking as "local" or "interprovin- cial" and was first asked by the Privy Council in respect of a bus service in the Winner case. In the AGT case, Madam Justice Reed, at page 175, noted that "the crucial feature then is the nature of the enterprise itself, not the physical equipment it uses". In the Dionne case, the Supreme Court referred to a "functionally inter-related system". When courts refer to the "essential nature" or to the degree of "functional integration" of an undertaking, what they have really considered is the overall purpose or function of the undertaking.
Parties who argued in favour of provincial jurisdiction in this case submitted that the purpose of the CCPI facilities was simply to transport natural gas between two points within Ontario. Analogy was made between the proposed CCPI facili ties and other gas distribution systems in Ontario which buy system gas from TransCanada and then distribute the gas to industrial, commercial and residential users within Ontario. The purpose of these gas distribution systems was contrasted with the TCPL system, whose purpose, it was submitted, is to transport natural gas from the western producing provinces to eastern Canada. It was submitted that the fact that CCPI purchased its gas in Alberta and that, unlike provincial gas distributors, it did not rely on system gas, was irrelevant in respect of the characterization of the CCPI facilities.
Parties who advanced the federal argument suggested that the true purpose of the CCPI facility was to complete the direct and continuous interprovincial transmission of natural gas,
purchased by CCPI in Alberta, to the proposed terminus of the CCPI pipeline in Welland, Ontario.
It was argued that the CCPI line was essential in order to effect that purpose and that the TCPL and CCPI pipeline systems would form an integral, indivisible and necessarily cooperative whole for the direct and continuous flow of natural gas from Alberta to the Cyanamid plant.
In examining what overall purpose the proposed facilities would serve, reference must be made to three important cases: the Luscar Collieries case, the Capital Cities case, and the Dionne case. The facts in these cases have been set out in Chapter 4 and there is no need to restate them here. In the Board's view, these cases are important because they closely parallel the facts before the Board in this case.
Parties who argued that the CCPI facilities would be a "local" work or undertaking made much of the fact that these facilities would be operated by CCPI and not by TCPL, the operator of an existing interprovincial undertaking. It was submitted that the Luscar case, unlike in the case now before the Board, the line in question was operated, pursuant to certain agreements, by CNR, which also operated a railway system extending from British Columbia to the rest of Canada.
In the Board's view, the mere fact that the Luscar line was operated by CNR is not significant in and of itself. What is important is the fact that, by virtue of such operation, the Luscar line became an upstream "link in a chain", which chain enabled traffic to pass to such parts of Canada as were served by the CNR system. The Luscar line itself was, in essence, a work whose purpose was to, inter alia, facilitate interprovincial traffic. In the present case, common operational agreements, as between TCPL and CCPI, are not required to enable traffic to pass over the TCPL system, through the CCPI system, to the ultimate consumer. TCPL is required, by virtue of orders issued by the Board, pursuant to subsection 59(2) of the NEB Act to transport and deliver gas offered by CCPI over the TCPL system to the point of connection with the proposed CCPI line. It is clear, therefore, that even without common operation as between CCPI and TCPL, the CCPI line is, as the Luscar line was, a "link in a chain", albeit a downstream link, which chain facilitates the direct and continuous interprovincial transmis sion of gas from its point of origin in Alberta to the Welland plant gate.
The Capital Cities and Dionne decisions relied on the "link in the chain" analogy as well. These cases involved the distribu tion by cable of "off-air" signals, which signals originated outside the province but which were received within the prov ince and then distributed to an end-user. In both of these cases, the Supreme Court emphasized that the Court was not deciding which level of government had jurisdiction over "local pro grams". The distinction between "local programs" and "off- air" programs is that the local programs are not received by the head-end as broadcast signals. So far as "local programs" are concerned, the cable system cannot be characterized as a "conduit for signals from a telecast" and does not constitute a
"link in the chain" of transmission from the transmitter to the end-user as is the case with "off-air" signals ....
Despite the recognition of "local" characteristics, the Supreme Court, in both the Capital Cities and the Dionne cases, refused to sever the cable component from the transmis sion and receiver portions of the broadcasting system ....
In coming to its decision in Capital Cities, the Supreme Court relied on, inter alia, the decision in the Winner case. Reference to the Winner case suggests to the Board that the Supreme Court drew parallels between the test that should be used for transportation cases and that which should be used in communication cases, where such cases involve a characteriza tion pursuant to paragraph 92(1)(a) of the Constitution Act, 1867.
The Board recognizes that it is not bound by the decisions in the Luscar, Capital Cities and the Dionne cases; however, given the similarities between the facts before the Board in this case and the facts before the Court in Luscar. Capital Cities and Dionne, the Board is of the view that it must be guided by the reasoning set out in those three decisions ....
Although the CCPI facility will be located entirely within the Province of Ontario, the Board cannot but conclude that these facilities will indeed form a downstream "link in a chain" which chain will facilitate the interprovincial transmission of gas from Alberta to the Welland plant. The fact that the Consumers' facilities currently serve the same purpose as the facilities proposed by the Applicant is, in the Board's view, immaterial to the characterization of the proposed facilities themselves.
5.3.6 Conclusion
The Board finds that the proposed facilities of CCPI are within the legislative authority of Parliament pursuant to sub section 91(29) and paragraph 92(10)(a) of the Constitution Act, 1867. In reaching this conclusion, the Board notes that while none of the characterization factors discussed above were, in and of themselves, sufficient to attract federal jurisdiction to the CCPI facilities, their combined effect persuades the Board that jurisdiction properly lies with Parliament.
Finally, the Board decided that its non-constitu tional jurisdiction is consequent upon the decision it had already arrived at regarding the constitu tional question (Reasons for Decision, ibid., at page 21):
5.5 Jurisdiction of the Board
The Board finds that the proposed CCPI facilities constitute a pipeline within the meaning of Section 2 of the NEB Act, and are, for this reason, under the jurisdiction of the Board, Section 2 of the NEB Act defines "pipeline" as:
"a line for the transmission of gas or oil connecting a province with any other or others of the provinces, or extend ing beyond the limits of a province or the offshore area as defined in section 87, and includes all branches, extensions,
tanks, reservoirs, storage facilities, pumps, racks, compres sors, loading facilities, interstation systems of communication by telephone, telegraph or radio, and real and personal property and works connected therewith;"
The definition of pipeline "tracks" the wording in paragraph 92(10)(a) of the Constitution Act, 1867. The board has found that the proposed CCPI facilities are part of an interprovincial undertaking connecting a province with any other or others of the provinces and fall within the exception enunciated in para graph 92(10(a). It follows, therefore, that the facilities also constitute a pipeline within the meaning of Section 2 of the NEB Act.
IV
Counsel for Union Gas Limited urged that the whole issue in this case ought to be resolved on the basis that the bypass pipeline in question is not a pipeline within the meaning of section 2 of the Act, since the Act contemplates only interprovin- cial works, and this pipeline, if within federal jurisdiction at all, could be only an interprovincial undertaking and not a work. There would there fore be no constitutional question to be answered.
This would in my opinion be at best a cumber- somely backhanded way of coming at the problem, since one of the very questions to be decided is whether the bypass line can be, constitutionally speaking, classed as an interprovincial work. Moreover, it is certainly not immediately evident that the correct interpretation of the section 2 definition is that it includes only works, and not undertakings. Further, it is, after all, only the constitutional issue which this Court has been requested to answer. If the Board were to misinter pret its Act, it would commit an error of law, which might be subject to review by this Court in another proceeding. But I do not find it necessary to answer this hypothetical question in order to dispose of the matter before the Court at the present time.
Turning, then, to the main issue, I believe it is best to begin with the cable-television analogy on which the Board placed so much emphasis. The Capital Cities and Dionne decisions of the Supreme Court of Canada, supra, involved the distribution by cable of "off-air" signals originat ing outside the province which were received
within the province and distributed to an end-user. The Board saw a close analogy between the pur pose served by the transmission cables in these cases and the proposed CCPI facilities. In its own words (supra, at page 19):
Both the cable system and the CCPI pipeline are dependent on the extraprovincial supply of a product. Neither delivery system, however, is necessary to the receipt, by end-users, of that product. Broadcast signals can be received directly by an antenna. Similarly, gas transported by TCPL to the Black Horse Station can be delivered to the Welland plant by means of an existing pipeline system. As well, in both instances, the consumers of the product are all located within one province; both the cable system and the proposed CCPI pipeline have a local character.
Superficially, the Board's comparison is correct. But in fact it should be made betwen pipeline and broadcasting transmission, not between pipeline and cable transmission, since the Supreme Court made it clear in the Capital Cities case, supra, that federal jurisdiction over the latter is a mere consequence of its jurisdiction over broadcasting. Chief Justice Laskin rejected the contention for provincial jurisdiction over cable transmission in these words, at pages 159 (S.C.R.); 198 (N.R.); 621 (D.L.R.):
The fallacy in the contention ... is in their reliance on the technology of transmission as a ground for shifting constitu tional competence when the entire undertaking relates to and is dependent on extra-provincial signals which the cable system receives and sends on to subscribers .... The system depends upon a telecast for its operation, and is no more than a conduit for signals from the telecast, interposing itself through a differ ent technology to bring the telecast to paying subscribers.
Cable transmission was thus held to be under federal jurisdiction as a part of a single undertak ing, which had already been determined to be within federal competence. In the instant refer ence, no party even argued that the pipelines bypassed (those of the LDC's) were under federal jurisdiction.
Taking the broader comparison, then, between natural gas systems and broadcasting systems, I
am more struck by the differences than by the similarities. As was rightly contended by counsel for Consumers', radio waves, when transmitted other than by cable, are not confined in space as gas is confined in a pipeline and so bear no rela tionship to territorial boundaries. Their reception, too, is virtually instantaneous. Professor Peter W. Hogg, Constitutional Law of Canada, 2nd ed., at page 501, puts the reason for not dividing broad casting on a territorial basis this way:
[R]adio is different from all of these other modes of transporta tion or communication in that all radio broadcasters must use the same kind of radio waves in the same frequency spectrum .... The need to allocate space in the frequency spectrum in order to avoid interference suggests that the power to regulate the interprovincial broadcaster must carry with it the power to regulate the intraprovincial broadcaster as well.
In the result, I find the broadcasting analogy singularly inapposite for natural gas pipelines.
Besides the Capital Cities and Dionne cases, the Board relied on a railway analogy based on the Luscar decision by the Judicial Committee of the Privy Council, supra. In the Luscar case the rail way line in question, although constructed and owned by an intraprovincial company, was oper ated on its behalf by the Canadian National Rail way. The Judicial Committee said, at pages 932-933:
Their Lordships agree with the opinion of Duff J. that the Mountain Park Railway and the Luscar Branch are, under the circumstances hereinbefore set forth, a part of a continuous system of railways operated together by the Canadian National Railway Company, and connecting the Province of Alberta with other Provinces of the Dominion. It is, in their view, impossible to hold as to any section of that system which does not reach the boundary of a Province that it does not connect that Province with another. If it connects with a line which itself connects with one in another Province, then it would be a link in the chain of connection, and would properly be said to connect the Province in which it is situated with other Provinces.
In the present case, having regard to the way in which the railway is operated, their Lordships are of opinion that it is in
fact a railway connecting the Province of Alberta with others of the Provinces, and therefore falls within s. 92, head 10 (a), of the Act of 1867. There is a continuous connection by railway between the point of the Luscar Branch farthest from its junction with the Mountain Park Branch and parts of Canada outside the Province of Alberta. If under the agreements here- inbefore mentioned the Canadian National Railway Company should cease to operate the Luscar Branch, the question wheth er under such altered circumstances the railway ceases to be within s. 92, head 10 (a), may have to be determined, but that question does not now arise.
Luscar has been authoritatively interpreted by the Supreme Court in the British Columbia Electric Ry. Co. Ltd. et al. v. Canadian National Ry. Co. et al., [1932] S.C.R. 161, at pages 169-170, where the Court said of the Luscar decision, in the course of arriving at a decision in favour of provincial jurisdiction over an electric railway line:
It was held that the Board had jurisdiction over the appel lant's lines constructed under provincial authority, because the line was part of a continuous system of railways operated together by the Canadian National Railway Company and connecting one province with another.
The decision is expressly put upon the way in which the railway is operated by the Canadian National Railway Com pany under the agreements, and it is intimated that if that company should cease to operate the appellant's branch, the question whether, under such altered circumstances, that branch ceases to be within s. 92, head 10 (a), might have to be determined. The question thus left undetermined is the very question that arises in the present case, because the Park line is not operated by the Canadian National Railway Company, nor by the appellant, the British Columbia Electric Railway Com pany, as the operator of the Vancouver & Lulu Island Railway, on behalf of the Canadian Pacific railway.
The mere fact that the Central Park line makes physical connection with two lines of railway under Dominion jurisdic tion would not seem to be of itself sufficient to bring the Central Park line, or the portion of it connecting the two federal lines, within Dominion jurisdiction.
With respect to a natural gas pipeline, a parallel situation would exist if TCPL had a similar agree ment to operate the CCPI pipeline. This would approximate the situation of the pipeline ter- minalling facilities in Dome Petroleum Ltd. v. National Energy Board (1987), 73 N.R. 135 (F.C.A.), which this Court held to fall under
federal jurisdiction. The Luscar case must there fore be distinguished.
Rather than trying to pick and choose among analogies, I believe a far sounder approach is to seek governing principles. In this context it is immediately apparent that in the vast majority of cases under paragraph 92(10(a) the courts have explicitly required the parties alleging federal jurisdiction to meet what the NEB initially termed the "vital, essential or integral to the undertaking" test, and then shortened to the "essential test", (supra, at pages 9-10). The Board itself cited the principal authorities for this test: Reference re Industrial Relations and Disputes Act, [1955] S.C.R. 529 (the Stevedoring Reference); Letter Carrier's [sic] Union of Canada v. Canadian Union of Postal Workers et al., [1975] 1 S.C.R. 178; Cannet Freight Cartage Ltd. (In re), [1976] 1 F.C. 174; (1976), 11 N.R. 606; (1975), 60 D.L.R. (3d) 473 (C.A.); Canadian National Railway Co. v. Nor-Min Supplies Ltd., [1977] 1 S.C.R. 322; Construction Montcalm Inc. v. Minimum Wage Commission, [1979] 1 S.C.R. 754; Northern Tele- com Ltd. v. Communications Workers of Canada, (#1), [1980] 1 S.C.R. 115; (#2), [1983] 1 S.C.R. 733. Whatever the terminology adopted, the courts say again and again in these cases that for a work or undertaking to fall under federal jurisdiction under paragraph 92(10)(a), it must either be an interprovincial work or undertaking (the primary instance) or be joined to an interprovincial work or undertaking through a necessary nexus (the secondary instance).
Indeed, I believe that even the cases which do not explicitly acknowledge this test affirm it implicitly. In the Luscar case the necessary nexus is the operating agreement; that is what makes the branch line a link in the interprovincial chain. In the cable television cases the necessary nexus is the inseparability of the medium and the message. As Chief Justice Laskin put it, in the Capital Cities
case, supra, at pages 162 (S.C.R.); 200 (N.R.); 623 (D.L.R.):
Programme content regulation is inseparable from regulating the undertaking through which programmes are received and sent on as part of the total enterprise.
The only authority which seems to resist the necessary nexus approach is the Winner case, supra. There an interprovincial (indeed, interna tional) bus system operating between Boston and Glace Bay, in addition to embussing and debussing extraprovincial passengers, also transported pas sengers between points entirely within New Bruns- wick. In upholding federal jurisdiction over the whole undertaking, the Judicial Committee of the Privy Council said, at page 581:
The question is not what portions of the undertaking can be stripped from it without interfering with the activity altogether; it is rather what is the undertaking which is in fact being carried on. Is there one undertaking, and as part of that one undertaking does the respondent carry passengers between two points both within the province, or are there two?
Since the Privy Council found the enterprise as actually carried on in Winner to be a primary instance of an interprovincial undertaking, that is, one having but a single participant with a single business, no question of a nexus arose, and the Supreme Court of Canada was declared wrong in having tried to strip away the incidental from the essential.
The Privy Council was, however, very careful to limit its holding to the exact facts, going so far as to say, at page 583:
Their Lordships express no opinion whether Mr. Winner could initiate a purely provincial bus service even though it was under the aegis of and managed by his present organization.
In such a further case it would seem that the issue of a nexus would loom large, even though only one organization was in question. The case of a primarily intraprovincial carrier, which is even farther removed from the facts in Winner, drew a more negative response from the Privy Council, at
page 582, with presumably even less possibility that a nexus could be established:
[T]heir Lordships must not be supposed to lend any counte nance to the suggestion that a carrier who is substantially an internal carrier can put himself outside provincial jurisdiction by starting his activities a few miles over the border. Such a subterfuge would not avail him. The question is whether in truth and in fact there is an internal activity prolonged over the border in order to enable the owner to evade provincial jurisdic tion or whether in pith and substance it is inter-provincial.
In the instant reference the NEB suggested that Winner and other cases gave rise to a so-called "purpose/nature of the undertaking" test, which attributed jurisdiction on the basis of the overall purpose of an enterprise. The typical case of this kind where federal jurisdiction was found is, how ever, one where there is a single business undertak ing: Toronto Corporation v. Bell Telephone Com pany of Canada, [1905] A.C. 52 (P.C.).
In fact, the closest parallel to the Winner situa tion in the instant reference would be an applica tion by TCPL to build and operate the bypass pipeline as its own. Failing that situation, it seems to me that the bypass line must meet the necessary nexus test in order to establish federal jurisdiction under 92(10)(a).
V
Counsel for CCPI cast his net in the broadest way by proposing in the alternative that the bypass pipeline was an interprovincial work and/or under taking of TCPL, or an interprovincial work and/or undertaking of CCPI.
In the Montreal City v. Montreal Street Rail way Company, [1912] A.C. 333 (P.C.), at page 342, works were said to be "physical things, not services." An undertaking, on the other hand, was defined In re Regulation and Control of Radio Communication in Canada, [1932] A.C. 304 (P.C.), at page 315, as "not a physical thing, but
... an arrangement under which of course physical things are used." As a work, the proposed pipeline exists solely within the province of Ontario and, as established by the B.C. Electric Railway case, supra, mere physical connection to the admittedly interprovincial TCPL work is not sufficient to found federal jurisdiction. If it is to come under 92(10)(a), I believe it must therefore be as an undertaking rather than as a work alone.
The NEB held, on the one hand, that the bypass pipeline was not part of an interprovincial under taking by CCPI, but that it was, on the other hand, an integral part of the undertaking of TCPL. It will be necesary to examine each of these possibilities in turn.
The interprovincial undertaking of CCPI was said to consist of the purchase of natural gas in Alberta, the transportation of that gas across Canada utilising the facilities of Nova (in Alber- ta), TCPL and CCPI itself, and the sale of the gas to Cyanamid at the Welland plant. In point of fact, at the present moment CCPI makes no gas purchases in Alberta or sales in Ontario, but as Cyanamid would presumably have transferred the Alberta contracts to its subsidiary by the time the pipeline was completed, I am prepared to decide the reference on the latter basis. However, to adapt a phrase of Judge Jerome Frank, I see this hypothesis as equivalent to a 2 percent tail wag ging a 98 percent dog. It would be a different situation if there were a two-way flow, as, for example, in passenger transportation or in broad casting, so that even the most infinitesimal part of the undertaking could be seen as necessary to the whole.
Moreover, in the Cannet case, supra, where the company in question was in the business of freight forwarding, this Court held, at pages 178 (F.C.); 611 (N.R.); 475 (D.L.R.), per Jackett C.J.:
In my view, the only interprovincial undertaking involved here is the Canadian National interprovincial railway. Clearly, a shipper on that railway from one province to another does not, by virtue of being such a shipper, become the operator of an interprovincial undertaking.
The interprovincial undertaking here is just as surely that of TCPL. An Ontario Divisional Court recently reached the same kind of conclusion in Re The Queen and Cottrell Forwarding Co. Ltd. (1981), 33 O.R. (2d) 486; 124 D.L.R. (3d) 674, where the parent company of the company in the Cannet case, also involved in the assembly, consoli dation and shipping of freight, was held to be under provincial jurisdiction. Steele J. said for the Court, at pages 492 (O.R.); 679-680 (D.L.R.):
The shipment is merely part of an over-all contract and a person who has no tangible or physical property under its [sic] control to operate an undertaking cannot, by contract, make himself a person carrying on an undertaking within the mean ing of s. 92(10)(a) of the British North America Act, 1867. Cottrell is not carrying on an undertaking or operation but is merely providing a service by contract.
Even if CCPI could be considered to be engaged in an interprovincial undertaking as understood in general commercial terms, it would not be an interprovincial undertaking of a transportation or communications character such as is required for federal jurisdiction under paragraph 92(10)(a). Professor Hogg, supra, at page 486, notes that this provision has never been held applicable to any work or undertaking which is not of a transporta tion or communications character, and argues that the phrase "other works and undertakings" should be read ejusdem generis with the specific examples which precede it, which are in every case modes of transportation or communication. I agree with this interpretation and with the conclusion of the NEB on this point. This was also the view of the Ontario Divisional Court on the OEB's stated case, supra, at pages 8-9.
On the other hand, the question whether the proposed pipeline is an integral part of the under taking of TCPL, for the reasons I have already
given it is impossible to evade the necessary nexus test as the Board did. Applying that test, I can find no such necessary connection. Far from being vital, essential, integral or necessary to TCPL, the proposed bypass is unnecessary and redundant.
TCPL already has an effectively functioning system which transports gas not only to the prov ince of Ontario but (with the aid of an LDC) to Cyanamid's Welland plant. TCPL has no need for anything more. The fact that it might be economi cally advantageous for an end-user to have its own pipeline has no corresponding advantage for TCPL, let alone any necessity.
The short (i.e. 6.2 kilometre) proposed pipeline has in fact more of the character of an individual connection than of an interprovincial undertaking. It would be one end-user's link with the main line, built for its own purposes. It is no more necessary to TCPL's function as an interprovincial transport er than any other end-user's connection to its supply line.
It was argued that CCPI's proposed commercial links with Alberta producers could be thought of as enlarging CCPI's nexus with TCPL's interpro- vincial undertaking. But even if CCPI's two aspects (as purchaser and as transporter) could be conceptualized as a single undertaking, then TCPL would have to be considered from the same twofold point of view—selling its own system gas (which it presently sells to LDC's) as well as transporting others' gas. In this enlarged perspec tive CCPI's proposed activities can appear only as even less necessary to TCPL's well-being.
Any argument beyond one based on the inter- provincial undertaking of TCPL, i.e. one resting, for example, on any perceived exigencies of nation al policy, would have to be cast in terms of the trade and commerce power, or the general power over peace, order and good government, arguments which the proponents of federal jurisdiction
expressly refrained from making on the present reference.
The Federal Parliament also, of course, retains the option of acquiring jurisdiction over any pipe line by declaring it to be a work for the general advantage of Canada under paragraph 92(10)(c) of the Constitution Act, 1867, but it has not chosen to exercise that power.
VI
I would therefore answer the question referred as follows:
The pipeline facilities proposed to be constructed and oper ated by Cyanamid Pipeline Inc. are not within the jurisdiction of the National Energy Board as not being within the legisla tive authority of the Parliament of Canada pursuant to subsec tion 91(27) and paragraph 92(10)(a) of the Constitution Act, 1867.
MAHONEY J.: I agree. STONE J.: I agree.
 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.