T-1952-87
Karl Mueller Construction Ltd. (Plaintiff)
v.
The Queen (Defendant)
INDEXED AS: KARL MUELLER CONSTRUCTION LTD. V. CANADA (T.D.)
Trial Division, Joyal J.—Edmonton, April 7; Ottawa, August 29, 1989.
Crown — Practice — Limitation of actions — Action against Crown on contract and in tort concerning road con struction work in Northwest Territories — Interpretation of contract to determine material facts — Burden on party asserting limitation — Contra proferentum rule — Cause of action not arising until engineer's certificate of final comple tion filed, at which time Crown's refusal to pay constituting breach — Earlier claim for payment and exercise of Crown's right to remove contract from plaintiffs hands immaterial — Federal Court Act, s. 39 and Crown Liability Act, s. 32 establish six-year limitation period with respect to cause of action arising otherwise than in province, whether in contract or tort — Alberta legislation governing limitation of actions not applicable as cause of action not arising in Alberta — Northwest Territories ordinance not applicable as not province.
Crown — Contracts — Action on contract for unpaid work — Work under road construction contract taken out of plain tiffs hands in October 1980 — Formal claim filed immediate ly — Final certificate of completion not filed until June, 1985 — Action commenced in 1987 — Action in contract not statute-barred — Cause of action arising upon filing of final certificate of completion, when Crown's refusal to pay con stituting actionable breach — Claim on contract merely claim on covenant to pay — Exercise of Crown's right to take contract out of plaintiffs hands not breach.
Crown — Torts — Highway construction projects — Whether rejection of six low bids over period of years mali cious, negligent — Not continuing tort — Separate claims timely except that regarding 1980 project — Alternative claim based on negligence, misrepresentation statute-barred.
This was a determination of questions of law upon an agreed statement of facts. The questions were: (1) whether the cause of action was statute-barred by either provincial or federal
legislation, and (2) which legislation applied. Work under a road construction contract was taken out of the plaintiffs hands prior to completion on October 1, 1980 on grounds of delay and lack of diligence. The contract provided that in such circumstances the engineer would determine the amount owing to the contractor. The plaintiff filed a formal claim on October 15, 1980. It was not until June 24, 1985 that the defendant filed a final certificate of completion of the contract. The plaintiff commenced an action on contract for unpaid work and in tort for damages, based upon allegations of misrepresenta tions in tender documents and negligence in the administration of the contract, on September 18, 1987. It also claimed dam ages for the malicious, negligent or unfair rejection of a number of its low-bid tenders for 1980, 1983, 1985, 1986 and 1987. The Crown argued that section 4 of the Alberta Limita tion of Actions Act barred the action on contract six years after the breach (i.e. October 1986). The plaintiff submitted that its claim did not arise until the engineer's final certificate of completion was filed. The issue was whether the alleged breach of the Crown's obligation to pay under the contract arose when the Crown took the contract out of the plaintiffs hands or at some later date. The Crown also submitted that the action in tort was similar to one for slander of title—a species of action in defamation—and was barred after two years by section 51 of the Alberta statute. The plaintiff argued that the Crown's actions in respect of the various contracts constituted a continu ing tort. Alternatively, if each rejection gave rise to a separate cause of action, and the six-year rule applied, only the 1980 rejection was statute-barred.
Held, the action on contract was not statute-barred under the applicable legislation—the Federal Court Act or the Crown Liability Act. The tort action was also timely except with regard to the 1980 construction project bid. The alternative claim based on negligence and misrepresentation was statute- barred in October, 1986.
A cause of action arises for the purposes of a limitation period when the material facts upon which it is based have been discovered. To determine the material facts it was necessary to scrutinize the contract provisions, bearing in mind that the burden rests on the party alleging limitation and that the interpretation of the contract must be more favourable to the plaintiff as it was drafted by the Crown (contra proferentum rule). The fact that the contract had been taken out of the plaintiffs hands and that the plaintiff immediately claimed payment had no legal significance with respect to the accrual of the cause of action. A claim on the contract was a claim on the covenant to pay in accordance with its terms. The exercise by the Crown of its right to take the contract out of the contrac tor's hands did not constitute a breach per se. The cause of action on the contract arose only upon the Crown's refusal to
pay upon the filing of the final certificate of completion. Many of the contract provisions were matters determinable by the engineer, and until the final certificate of completion was issued and the Crown refused to pay there was no actionable breach.
The Crown's conduct did not constitute a continuing tort. A series of independent or separate actions, perhaps by different people at different times, which result in one particular type of damage is not a continuing tort. The alternative claim based on negligence and misrepresentation was statute-barred as of October, 1986, but the separate claims in tort (except that relating to the 1980 highway construction project) were timely.
The action was instituted against the federal Crown and the Federal Court had exclusive jurisdiction to hear it. Section 39 of the Federal Court Act and section 32 of the Crown Liability Act provide that provincial limitations laws apply to proceed ings in respect of any cause of action arising in that province, but that proceedings in respect of a cause of action arising otherwise than in a province shall be taken within six years after the cause of action arose. The Limitation of Actions Act of Alberta did not apply because the cause of action arose in the Northwest Territories. The Limitation of Actions Ordi nance of the Northwest Territories did not apply because the Northwest Territories is not a province. The limitation period was six years under either the Federal Court Act or the Crown Liability Act whether the action was founded on contract or in tort.
STATUTES AND REGULATIONS JUDICIALLY CONSIDERED
Crown Liability Act, R.S.C., 1985, c. C-50, s. 32. Federal Court Act, R.S.C., 1985, c. F-7, s. 39.
Federal Court Rules, C.R.C., c. 663, R. 474.
Limitation of Actions Act, R.S.A. 1980, c. L-15, ss. 4, 51. Limitation of Actions Ordinance, R.O.N.W.T. 1974, c. L-6, s. 3.
CASES JUDICIALLY CONSIDERED
APPLIED:
Rittinger Construction Ltd. v. Clark Roofing (Sask.) Ltd. (1967), 65 D.L.R. (2d) 158 (Sask. Q.B.); affd (1968), 68 D.L.R. (2d) 670 (Sask. C.A.).
CONSIDERED:
Kamloops (City of) v. Nielsen et al., [1984] 2 S.C.R. 2; Central Trust Co. v. Rafuse, [ 1986] 2 S.C.R. 147.
REFERRED TO:
Mott v. Trott, [1943] S.C.R. 256; McBride v. Vacher & Vacher, [1951] 2 D.L.R. 274 (Ont. C.A.); Power v. Halley (1981), 124 D.L.R. (3d) 350 (Nfld. C.A.).
AUTHORS CITED
Fleming, John G. The Law of Torts, 7th ed. Sydney: Law Book Company, 1987.
Halsbury's Laws of England, 4th ed. London: Butter- worths, 1987.
Heuston, R. F. V. and Buckley R.A. Salmond and Heus- ton on The Law of Torts, 19th ed. London: Sweet & Maxwell, 1977.
Linden, Allen M. Canadian Tort Law, 4th ed. Toronto: Butterworths, 1988.
COUNSEL:
Bruce E. Mintz for plaintiff. Kirk Lambrecht for defendant.
SOLICITORS:
Lefsrud, Coulter & Kerby, Edmonton, for plaintiff.
Deputy Attorney General of Canada for defendant.
The following are the reasons for judgment rendered in English by
JOYAL J.: On September 18, 1987, the plaintiff issued a statement of claim in this Court claiming various heads of damages against the defendant Crown.
The claim originally arose out of a road con struction contract awarded to the plaintiff by the Department of Public Works on January 10, 1979, for the Liard Highway project in the Northwest Territories. During the performance of the con tract, the work was taken out of the plaintiff s hands on grounds of delay and lack of diligence. The plaintiff claims that this was unjustified and that fault lay with the Crown by reason of the Crown's own misrepresentations and negligence with respect to the nature of the work to be performed. The plaintiff claims an amount of some $500,000 for unpaid work and damages.
Further, the plaintiff claims that in a number of tenders for other road construction work submitted during the period 1980-1987, and in which the plaintiff was the lowest bidder, the defendant mali ciously, capriciously, negligently or unfairly, rejected the plaintiffs bids. For this the plaintiff claims general damages of $300,000 and punitive damages of $100,000.
In its statement of defence, the Crown alleges, inter alia, that the cause of action in contract as well as the cause of action in tort are statute- barred by the reason of section 4 and section 51 of the Limitation of Actions Act, R.S.A. 1980, c. L-15. Section 4 provides for a six-year limitation for an action on contract and section 51 provides for a two-year limitation on actions in tort.
Subsequently, the parties agreed to submit the question of limitation to a determination by this Court pursuant to Rule 474 of the Federal Court Rules [C.R.C., c. 663]. The parties agreed on a statement of facts and set down the question of law as follows:
Whether the plaintiffs action is barred in whole or in part by the application or any of all of the following statutes:
(a) Federal Court Act, R.S.C., 1985, c. F-7, section 39;
(b) Limitation of Actions Act, R.S.A. 1980, c. L-15, sections 4 and 51;
(c) Limitation of Actions Ordinance, R.O.N.W.T. 1974, c. L-6, section 3; and
(d) Crown Liability Act, R.S.C., 1985, c. C-50, section 32.
THE FACTS
The plaintiff's contract with the Crown was for a three-mile stretch of the Liard Highway in the Northwest Territories. The plaintiff proceeded with the contract from the date of the award on January 10, 1979 until October 1, 1980, when the work was taken out of its hands pursuant to clause 16 of General Conditions "C" of the contract. In this clause, the Crown reserves the right to take over a contract when there is delay or default or lack of diligence which goes unremedied after a
certain notice period. Once such action has been taken by the Crown, clause 16 goes on to say:
16....
(2) Where the work or any portion thereof has been taken out of the Contractor's hands under subsection (1) the Contractor shall not except as provided in subsection (3), be entitled to any further payment including payments then due and payable but not paid and the obligation of Her Majesty to make payments as provided for in the Terms of Payment shall be at an end and the Contractor shall be liable to and upon demand therefor pay to Her Majesty an amount equal to all loss and damage suffered by Her Majesty by reason of the non-completion of the work by the Contractor.
(3) Where the work or any portion thereof has been taken out of the Contractor's hands under subsection (1) and that portion is subsequently completed by Her Majesty, the Engineer shall determine the amount, if any, of holdback and progress claims of the Contractor unpaid at the time of taking the work out of his hands that in his opinion are not required by Her Majesty for the purposes of the contract and the Minister shall, if he is of the opinion that no financial prejudice to Her Majesty will result, authorize payment of that amount to the Contractor.
Clause 17 also provides that:
17.(1) The taking of the work, or any portion thereof, out of the Contractor's hands pursuant to section 16 of the General Conditions does not operate so as to relieve or discharge the Contractor from any obligation under the contract or imposed upon him by law except the obligation to complete the physical execution of that portion of the work so taken out of his hands.
On October 15, 1980, the plaintiff filed a formal claim with the defendant in the sum of $575,000. A few months later, on January 31, 1981, the plaintiff filed a supplemental claim in the sum of $67,000.
Between 1981 and 1985, the plaintiff unsuccess fully sought payment of the foregoing sums from the defendant.
It was only on June 24, 1985 that the defendant, pursuant to the contract, filed a final certificate of completion of the contract. This was followed on October 29, 1985 with an offer by the defendant to pay the plaintiff the sum of $19,090.06 as final payment under the contract. The plaintiff did not accept this offer and some two years later, on September 18, 1987, instituted its action on con tract. To that action of course was joined its action in tort to which I have already referred but as the limitations applicable to contracts and torts might
be different, I shall defer to later the consideration involving that part of the case.
THE ACTION ON CONTRACT
I. Position of the Crown
It is the Crown's position that the plaintiffs claim is divisible in three parts. There is the action on the contract which was taken out of the plain tiffs hands on October 1, 1980 and on which a claim for damages for breach of it, for misrepre sentations in the tender documents and for negli gence in the administration of the contract, are founded. If a breach of contract occurred, argues the Crown, the limitation date starts to run from the date of the breach and the action became statute-barred some six years later, i.e., on or about October, 1986.
The Crown acknowledges, however, that the second claim in contract, that one arising from the dispute over the Crown's final determination of moneys owing pursuant to its final certificate of completion on June 24, 1985, is not statute-barred.
II. Position of the Plaintiff on the Contract
The plaintiff's approach is primarily based on the nature of the contract entered into with the Crown and on the various provisions relating to the method of its costs calculations and to payment of these costs.
The plaintiff states that the contract was on a unit price basis involving both quantities and vari ous types of soil conditions. It was by reason of miscalculation by the Crown in these matters that the plaintiff suffered considerable cost overruns which give rise to a quantum meruit type of claim. The contract establishes payment terms for this unit price work in Article II of the Articles of Agreement. The quantification of the payment itself is based on a formula which contemplates additions or amendments or an application of sec tion 46 of the General Conditions "C". In clause 2 of this section, there is found a detailed formula to
determine any amount owing which, on an analysis of it, is no more, no less than quantum meruit.
Further, says the plaintiff, the engineer appoint ed under the contract, is vested with a discretion in dealing with changes in soil conditions as well as with evaluating claims for extras, the whole to make sure that the "burden of substantial increase in cost will not be borne by the contractor".
According to the plaintiffs interpretation of the contractual links between the parties, its claims of October 15, 1980 and of January 31, 1981, remained outstanding and in limbo pending the engineer's final certificate of completion which was filed on June 24, 1985. That certificate states:
Revised Unit Prices determined by the Engineer as a fair and reasonable settlement in accordance with Articles of Agree ment, Article II(2)(e).
The plaintiff concludes that cost overruns under the contract are determined on a quantum meruit basis as the overruns might be determined by the engineer. In exercising his authority in this respect, the engineer must decide what in any event is required of the contractor under its contract and what is the nature and extent of the soil conditions which cause a substantial increase in the contrac tor's costs.
As a result, the plaintiffs claim cannot arise until the engineer's final certificate of completion is filed. It is at that time that the plaintiffs claim becomes crystallized and it is at that time that the cause of action arises. Finally, it is at that time that the Crown's failure to pay constitutes an actionable breach of contract.
THE FINDINGS ON THE ACTION ON CONTRACT
The ground rule with respect to determining the commencement of a limitation period with respect to any cause of action was expressed in Kamloops (City of) v. Nielsen et al., [1984] 2 S.C.R. 2, and restated by Le Dain J. in Central Trust Co. v.
Rafuse, [1986] 2 S.C.R. 147, when he said, at page 224:
I am thus of the view that the judgment of the majority in Kamloops laid down a general rule that a cause of action arises for purposes of a limitation period when the material facts on which it is based have been discovered or ought to have been discovered by the plaintiff by the exercise of reasonable diligence ....
The wording of this general rule seems quite simple. Its application, however, is somewhat more difficult and it calls upon the court to make a determination as to what facts are the material ones to cause the clock to start ticking in respect of the commencement of the appropriate limitation period.
In general, in contract cases, it has been held that the limitation begins to run from the occur rence of the breach of contract. The cases of Mott v. Trott, [1943] S.C.R. 256; McBride v. Vacher & Vacher, [1951] 2 D.L.R. 274 (Ont. C.A.); Power v. Halley (1981), 124 D.L.R. (3d) 350 (Nfld. C.A.), all confirm this proposition. The issue before me is therefore whether or not the alleged breach of the Crown's obligation to pay under the contract occurred at the time the Crown unilater ally took the contract out of the plaintiffs hands and subsequently failed to pay demands for pay ment over the years 1980 to 1985, or whether the contractual breach for failure to pay arose at some subsequent date.
Needless to say, for anyone who is familiar with construction contracts involving the Crown, their terms and conditions, built up over the many years through the brick by brick method, are not always clear in their meaning or in their conformity.
The Articles of Agreement filed in the record contain six small-print pages. This document is followed by Schedule "B" entitled "Terms of Pay ment" which run through four small-print pages. The whole is followed by General Conditions "C" which contain 48 sections running through 18 pages of equally fine print. There are as well other appendices pertaining to Class of Labour, Plant and Material, Estimated Quantity and Price per Unit, and to Labour Conditions as well as to
Classification of Labour including applicable rates of pay for some 67 different trades or occupations. I might add that all the substantive provisions of these contract documents are drafted or printed by the Crown. They constitute what civil law calls "contrats d'adhésion" and the contra proferentum rule applies to favour the plaintiff.
In any event, there is imposed on the Court the obligation to scrutinize the various interactive provisions of such contracts keeping in mind two fundamental precepts, namely that in matters of limitation, the burden to prove it rests on the party alleging it and, if this involves the interpretation of certain ambiguities in the contract documents themselves, the interpretation, for reasons previ ously stated, must be one more favourable to the plaintiff.
For example, in Rittinger Construction Ltd. v. Clark Roofing (Sask.) Ltd. (1967), 65 D.L.R. (2d) 158 (Sask. Q.B.); affirmed in (1968), 68 D.L.R. (2d) 670 (Sask. C.A.), the Court was faced with the problem of the proper construction of a contract to determine when the limitation clock would start to run. The contract was for the construction of a roof and it provided for the contractor to remedy defects within one year of completion. Such defects appeared and attempts to remedy them were unsuccessfully made over the next four years. The six-year limitation was raised but the Court held that the time started to run not from the date of completion but from the time the last attempt was made to remedy the defects or at least from a year after the contract was substan tially completed.
In the contractual documents before me, I should single out the following provisions:
(1) Under Terms of Payment "B", clause 6, a delay by the Crown in making payment in respect of any sum due and payable "shall be deemed not to be a breach of the contract".
(2) Under Terms of Payment "B", clause 4, as read together with General Conditions "C", clause 16(3), the Crown is only legally bound to pay any outstanding amounts due to the plain tiff upon the expiration of 60 days from the issuance of a certificate of final completion.
(3) Under Terms of Payment "B", clause 5, a clause which reflects the accrual method of payment provided for in clause 4, any progress report or any payment by the Crown shall not be construed as evidence that the work, material or any part thereof is complete, is satisfactory or is in accordance with the contract.
My interpretation of these clauses, whether or not they were inserted there by the Crown for purposes of providing generous limitation periods to an unhappy contractor, which I seriously doubt, is that they provide that, a cause of action, based on the breach of the covenant to pay, cannot arise until the Crown is legally bound to pay the plain tiff and refuses to do so. The fact that the contract was taken out of the plaintiff's hands and that the plaintiff immediately claimed payment on account of it, would have, in my opinion, no legal signifi cance with respect to the accrual of the plaintiff's cause of action. Had the plaintiff taken immediate action after the contract was taken out of its hands, the Crown, by relying on the same provi sions, could have claimed that the payments were not yet contractually due.
As I see it, a claim on this contract is a claim based on the breach of the Crown's covenant to pay in accordance with its terms. The exercise by the Crown of its right to take the contract out of the contractor's hands under General Condition "C", clause 16, does not appear to me to constitute a breach per se. In fact, clause 17 stipulates that in such an event, the plaintiff remains contractually bound to all the terms and conditions of the con tract except to complete that portion of the work taken out of its hands.
I should observe that it would be difficult for me to conclude that on the one hand, a contract subsists for the purposes of binding a party to fulfil its obligations but that it does not survive with respect to the payment covenants beyond the point when the contract is taken over.
I should therefore subscribe to the plaintiff's view that the cause of action on the contract arises only upon the Crown's refusal to pay upon the filing of the final certificate of completion. It is only as of that date that the plaintiff is certain that the Crown is in fact refusing to pay what the plaintiff felt is properly owed and is thus in breach of the contract. By the nature of the contract many of the other contract provisions (including the determination of what constitutes entire quan tities or what unit prices are payable depending upon the nature of the anticipated soil conditions, or generally what cost overruns are properly the responsibility of the plaintiff or are at the charge of the Crown), are matters determinable by the engineer under General Conditions "C", clause 34 and clause 12 or under Articles of Agreement, Article II, s. (2). Until all of this is done (resulting in the issuance of the final certificate of comple tion), and the Crown refuses to pay, there is no actionable breach of contract. Under that head, therefore, and assuming that the applicable limita tion period is six years, the plaintiff's claim is not statute-barred.
Admittedly, the plaintiff makes an alternative claim under the same head but which in terms of negligence or misrepresentation alleged against the Crown, has the earmarks of an action in tort. In such event, a different limitation period might apply and it could be argued that the material facts on which this claim is based was known to the plaintiff as early as 1980. Plaintiff's counsel concedes that the statement of claim may require an amendment to further clarify these two distinct causes. Given the flexibility in amendments to
pleadings, I should leave such matter to the initia tive of counsel, and to determination at trial.
THE ACTION IN TORT
I. Position of the Crown
Crown counsel interprets this action as one analogous to an action for slander of title. It is a species of an action in defamation. Counsel claims that this is governed by the two-year limitation rule, i.e. that any claim in relation to damage which occurred before September 18, 1985 is untimely.
II. Position of the Plaintiff
In accordance with the agreed statement of facts, low bids were submitted by the plaintiff for various Crown projects in the years 1980, 1983, 1985, 1986 and 1987. Some six bids in total were rejected by the Crown and the plaintiff views this action as malicious, unfounded, capricious, negli gent and unfair. The plaintiff claims loss of profits on these contracts totalling $565,000.
The plaintiff submits that these events, running from 1980 to 1987, are on a continuing basis. In the alternative, if each rejection constitutes a sepa rate cause of action, only the 1980 rejection would be statute-barred if the six-year rule is found applicable.
THE FINDINGS ON ACTION IN TORT
Whether or not the actions taken by the Crown in respect of all these contracts constitute a con tinuing tort or a continuing cause of action is not easy to determine. Fleming's The Law of Torts, Salmond and Heuston's The Law of Torts or Linden's Canadian Tort Law and Halsbury's Laws of England do not appear to define what constitutes a continuing tort or, in any event,
would not appear to cover any case where the facts are as singular and peculiar as the ones before me.
It could be said that in the mind of any plaintiff, a tort does not necessarily occur by reason of the first rejection. It might not even come to mind by reason of the second rejection. It should therefore be over a certain period of time that the accumula tion of rejections would provide the material facts on which a claim in tort could be founded. In such case, the various rejections might lead to a finding that there exists a continuing tort.
On the other hand, it could be argued that for a tort to be considered continuing, it must arise out of conduct which results in damages or conse quences continuing over a certain period of time. It is therefore not the tort in itself which is necessari ly repeated, but its consequences which either flow or continue by design or by circumstance. Such could be the case in the case of a continuing trespass.
I should find that the conduct of the Crown cannot be construed as a continuing tort. A series of independent or separate actions, perhaps by different people at different times, which result in one particular type of damage, may not be called a continuing tort. As an example, if a defamatory pamphlet is written and distributed by someone and excerpts from this pamphlet are later pub lished by a magazine or newspaper, such might be a continuing tort giving rise to one cause of action. However, if a succession of different defamatory pamphlets are written and distributed by different people on a number of different dates, any liability for these acts would have to be treated on a case-by-case basis and not under one cause of action.
More than that, on the basis of the agreed statement of facts, I am unfortunately unable to say more. If in a normal tort action as stated in the Kamloops case supra, a cause of action arises for the purposes of a limitation period where the material facts on which it is based have been
discovered or ought to have been discovered by the plaintiff, I have no evidence before me to make a finding on it. I must again leave that issue to determination at trial. As will be seen, however, even by adopting the scenario most favourable to the Crown, most, if not all of the separate claims might still come within the limitation period.
THE APPLICABLE STATUTE
The question of law before the Court as to the applicable limitation statute must now be studied.
The case states four statutes, namely the Feder al Court Act, the Crown Liability Act and the Limitation of Actions Act of Alberta and the Limitation of Actions Ordinance of the Northwest Territories.
It is a fact that the action instituted by the plaintiff is against the Federal Crown and that the Federal Court of Canada has exclusive jurisdiction to hear it. It is also a fact the plaintiff is incorpo rated in the Northwest Territories and that the performance of the contract was in that jurisdic tion. The additional fact, however, that the plain tiff's action was instituted in the Edmonton Regis try is, in my view, immaterial to a determination of which of the foregoing statutes apply.
Limitations on proceedings in the Federal Court are provided in section 39 of the Federal Court Act which reads as follows:
39. (1) Except as expressly provided by any other Act, the laws relating to prescription and the limitation of actions in force in any province between subject and subject apply to any proceedings in the Court in respect of any cause of action arising in that province.
(2) A proceeding in the Court in respect of a cause of action arising otherwise than in a province shall be taken within six years after the cause of action arose.
(3) Except as expressly provided by any other Act, the laws, relating to prescription and the limitation of actions referred to in subsections (1) and (2) apply to any proceedings brought by or against the Crown.
I note in terms of this foregoing provision that provincial limitation rules generally apply in respect of any cause of action arising in that province. However, if no other federal statute so provides and if a cause of action arises otherwise than in a province of Canada, it follows that a six-year limitation applies.
A similar limitation provision is found in the Crown Liability Act. Subsection 32(1) states as follows:
32. (1) Unless otherwise provided in this Act, the laws relating to prescription and the limitation of actions in force in a province between subject and subject apply to any proceed ings against the Crown under this Act in respect of any cause of action arising in that province, and proceedings against the Crown under this Act in respect of a cause of action arising otherwise than in a province shall be taken within six years after the cause of action arose.
The conformity between that provision and the one found in the Federal Court Act is obvious. Both apply the six-year limitation rule whenever a cause of action arises otherwise than in a province.
By adopting a process of elimination, it would appear that the Limitation of Actions Act of Alberta cannot apply because the cause of action did not arise in that province. The Limitation of Actions Ordinance of the Northwest Territories cannot apply where the Crown is involved, because the Northwest Territories is not, at least as yet, constituted as a province. It follows that federal law, as enacted under either the Federal Court Act or the Crown Liability Act, would determine the period of limitation in the action before me. This limitation period is six years whether the action be founded on contract or in tort. As a further conse quence, it matters not whether the plaintiff's tort action is one of slander, libel, defamation or other wise. The action is governed by the six-year rule.
In answer to the stated questions, therefore, I should conclude that the plaintiff's action on con tract is not statute-barred under the provisions of the Federal Court Act or of the Crown Liability Act. The plaintiff's action in tort is similarly
timely except as to the action relating to the refusal of the Crown to accept the plaintiff's low bid for the construction of another section of the Liard Highway in 1980. For reasons already stated, the status of that particular head of claim should be left to the trial judge. In any event, it is a question of mixed fact and law which should not be determined under Rule 474.
I should also conclude that the plaintiff's alter native claim on grounds of negligence and mis representation, as currently framed in the plead- ings, is statute-barred as of October 1, 1986.
The costs of these proceedings should be in the cause.