Judgments

Decision Information

Decision Content

T-2985-84
Pembina Resources Limited and Pembina Exploration Co. Ltd. (Plaintiffs)
v.
ULS International Inc., Canada Steamship Lines Inc., Halco Inc., Nipigon Transport Ltd., Cleve- land Tankers Inc., Wilmington Trust Company, American Steamship Co. Inc., Boland and Cor- nelius, Her Majesty the Queen in Right of Canada and the ships Canadian Hunter, Canadian Cen tury, Canadian Transport, Canadian Progress, Manitoulin, Island Transport, Laketon (formerly the Lake Nipigon), Saturn and Sam Laud and their owners and charterers (Defendants)
[By original action] and
Pembina Resources Limited and Pembina Exploration Co. Ltd. (Plaintiffs)
v.
ULS International Inc. and the ship Canadian Hunter and its owners and charterers (Defen- dants)
[As amended by virtue of discontinuances of action filed in the cause]
INDEXED AS: PEMBINA RESOURCES LTD. V. ULS INTERNA TIONAL INC. (T.D.)
Trial Division, McNair J.—Toronto, February 21, 22, 23, 24, 27 and 28, March 1, 2, 14 and 15; Ottawa, October 6, 1989.
Negligence — Submerged natural gas pipeline fractured by ship's dragging anchor — Negligence of captain — Contribu tory negligence argument rejected — Omission to mark pipe line's location with radar sensitive buoys not effective cause of damage — Estimated cost of permanent repairs awarded as damages for prospective loss — General damages awarded for business interruption — Application of U.S. decisions affirm ing principle of damage recovery for loss of production — Lost profits proper means of measuring damages — Latter assessed on basis of current value of lost production — Plaintiffs' intervening act (failure of divers to correctly reassemble faulty couplings) not absolving defendants from liability.
Maritime law — Torts — Submerged natural gas pipeline fractured by dragging anchor — Negligence of captain —
Failure to mark location using radar sensitive buoys and to bury pipeline not contributing to damage as not effective cause thereof.
Maritime law — Practice — Submerged natural gas pipe line fractured by ship's anchor — Negligence of captain — General damages for business interruption — Admiralty prac tice of allowing pre-judgment interest from date of injury followed — Lack of case law and novelty of issues not special considerations justifying denial of interest.
The plaintiffs' action is for damages resulting from the fracture, on December 24, 1983, of a segment of their sub merged natural gas pipeline (the "inner bay line") in Long Point Bay, Lake Erie. The fracture is alleged to have been caused by the dragging anchor of the defendant ship, the Canadian Hunter. Temporary repairs were not completed until April 3, 1984. Full production resumed on April 5, 1984. Rather than make permanent repairs, the plaintiffs chose to lay a new pipeline in a different location.
The plaintiffs seek to recover the costs of temporary repairs and the estimated costs of permanent repairs. The parties are agreed as to the quantum of those costs but not as to liability therefor. The plaintiffs also claim general damages for loss of business income. They submit that liability lies with those responsible with the management and operation of the defen dant ship. The defendants plead voluntary assumption of risk on the part of the plaintiffs and, alternatively, contributory negligence.
Held, the action should be allowed.
The evidence showed that the Canadian Hunter was the only vessel which could, by its position, have snagged the plaintiffs' pipeline and that it did in fact do so. The evidence also established that the captain of the Canadian Hunter had been negligent (1) in choosing an anchorage area situated less than one mile from the pipeline and poorly protected from the adverse weather conditions prevailing at the time; (2) in per mitting his vessel to drag its anchor for a mile and a half without taking any corrective measures; (3) in failing to have aboard the most up-to-date navigational charts available; and (4) in failing to check his ship's position regularly.
The defendants' argument based on contributory negligence was rejected. For contributory negligence to be found, there must be evidence that the negligence "was a proximate, in the sense of effective, cause of injury". The plaintiffs' failure to mark the location of the pipeline by appropriately spaced and radar sensitive spar buoys did not constitute a fault or omission that contributed to the damage complained of in the sense of being an effective cause thereof. Nor were the plaintiffs at fault by not burying the pipeline: such a measure was neither a reasonable nor a viable means of avoiding the foreseeable risk of injury by a ship's anchor.
Since the cost of temporary repairs was not in issue, the plaintiffs were entitled to recover the amount agreed upon as damages flowing from the injury. The plaintiffs were also
entitled to recover the estimated cost of permanent repairs. The fact that the permanent repairs were not carried out was of no consequence. As stated in McGregor On Damages, "Since damages may ... be given for prospective loss, it is immaterial that the repairs are not yet executed." Permanent repairs were a prospective loss which the defendants should reasonably have foreseen as a consequence of their negligence.
There were few Canadian authorities dealing with business interruption claims of the nature discussed herein. Reference was made to American decisions, and the principle expounded therein, that damages are recoverable for loss of production, was applied. Such damages may be measured in terms of lost profits. In the case at bar, the damages were to be assessed on the basis of the current value of lost production. To adopt the defendants' theory that interruption effected a mere deferral of production and that the current value of the production that might ultimately be recovered should be deducted from the current value of the lost production would be inequitable in that it would fail to take into account the inconvenience and delay suffered by the plaintiffs during the shut-down period. The question whether the plaintiffs could have made up the lost production was irrelevant. Whatever occurs after the loss does not affect the right to recover damages for lost production.
Damages for loss of business income were to be calculated from the date of the fracture of the pipeline to the date full production resumed (a total of 104 days). The defendants' argument that failure of the plaintiffs' divers to correctly reassemble all the faulty couplings within 60 days constituted an intervening force which absolved them from liability, was rejected. Liability still lies with the original wrongdoer where the intervening act is one which ought reasonably have been foreseen by that wrongdoer. In the case at bar, the failure of plaintiffs' divers constituted an intervening force which the defendants should reasonably have anticipated as being a likely consequence of their original negligence.
A claim for damages for loss of use cannot be allowed unless the plaintiff proves actual loss. The plaintiffs had discharged that onus: there was ample evidence of loss of profits during the 104-day shut-down.
The practice in admiralty cases to allow pre-judgment inter est as an integral part of the damages awarded was followed. The plaintiffs were granted pre-judgment interest from the date of the injury to the date of judgment at the agreed rate of 9.5%. Lack of case law and the novelty of the issues raised do not constitute special considerations which could support exercise of the Court's discretionary power to refuse interest for the period sought.
STATUTES AND REGULATIONS JUDICIALLY CONSIDERED
Navigable Waters Protection Act, R.S.C. 1970, c. N-19,
s. 5(1).
Negligence Act, R.S.O. 1980, c. 315.
O. Reg. 629/80, s. 2.
O. Reg. 450/84.
Petroleum Resources Act, R.S.O. 1980, c. 377.
R.R.O. 1980, Reg. 752, s. 27(13).
The Energy Act, 1971, S.O. 1971, c. 44.
CASES JUDICIALLY CONSIDERED
APPLIED:
Bell Telephone Co. v. The Mar-Tirenno, [1974] 1 F.C. 294; 52 D.L.R. (3d) 702 (T.D.); affd [1976] 1 F.C. 539; 71 D.L.R. (3d) 608 (C.A.); Rose et al. v. Sargent, [1949] 3 D.L.R. 688; [1949] 2 W.W.R. 66 (Alta. C.A.); McLoughlin v. Long, [1927] S.C.R. 303; [1927] 2 D.L.R. 186; The London Corporation, [1935] P. 70 (C.A.); Fitzner v. MacNeil (1966), 58 D.L.R. (2d) 651 (N.S.S.C.); Martin v. McNamara Construction Com pany Limited and Walcheske, [1955] O.R. 523; [1955] 3 D.L.R. 51 (C.A.); Continental Oil Co. v. S S Electra, 431 F.2d 391 (5th Cir. 1970); National Steel Corp. v. Great Lakes Towing Co., 574 F.2d 339 (6th Cir. 1978); U. S. Oil of Louisiana, Ltd. v. Louisiana Power & Light Co., 350 So. 2d 907 (La. Ct. App., 1st Cir. 1977); Canadian General Electric Co. Ltd. v. Pickford & Black Ltd., [1972] S.C.R. 52; (1971), 20 D.L.R. (3d) 432; Drew Brown Ltd. v. The "Orient Trader", [1974] S.C.R. 1286.
DISTINGUISHED:
Bolivar County Gravel Co., Inc. v. Thomas Marine Co., 585 F.2d 1306 (5th Cir. 1978).
CONSIDERED:
Assiniboine (School Division of) South No. 3 v. Hoffer et al. (1971), 21 D.L.R. (3d) 608; [1971] 4 W.W.R. 746 (Man. C.A.); The Ship Peterborough v. Bell Telephone Co. of Canada, [1952] Ex.C.R. 462; [1952] 4 D.L.R. 699; Pacific Elevators Ltd. v. Canadian Pacific Railway Co., [1974] S.C.R. 803; (1973), 41 D.L.R. (3d) 608.
REFERRED TO:
Exeter City v. Sea Serpent (1922), 12 LI. L. Rep. 423 (Adm. Div.); The Brabant (1938), 60 Ll. L. Rep. 323 (Adm. Div.); The Boltenhof (1938), 62 LI. L. Rep. 235 (Adm. Div.); The Velox, [1955] 1 Lloyd's Rep. 376 (Adm. Div.); The Gerda Toft, [1953] 2 Lloyd's Rep. 249 (Adm. Div.); Canadian Brine Ltd. v. The Ship Scott Misener and Her Owners, [1962] Ex.C.R. 441; Subma rine Telegraph Company v. Dickson (1864), 15 C.B. (N.S.) 760; 143 E.R. 983 (C.P.D.); Heeney v. Best et al. (1979), 28 O.R. (2d) 71; 108 D.L.R. (3d) 366; 11 CCLT 66 (C.A.); Northern Wood Preservers Ltd. v. Hall Corp. (Shipping) 1969 Ltd. et al., [1972] 3 O.R. 751; (1972), 29 D.L.R. (3d) 413 (H.C.); affd (1973), 2 O.R. (2d) 335; 42 D.L.R. (3d) 679 (C.A.); R. in right of Canada v. Saskatchewan Wheat Pool, [1983] 1 S.C.R. 205; 143 D.L.R. (3d) 9; [1983] 3 W.W.R. 97; 23 CCLT 121; 45
N.R. 425; Walls v. MacRae and Metro Fuels Co. Ltd. (1981), 36 N.B.R. (2d) 1; 94 A.P.R. 1 (Q.B.); Total Petroleum (N.A.) Ltd. v. AMF Tuboscope Inc. (1987), 81 A.R. 321; 54 Alta. L.R. (2d) 13 (Q.B.); Norcen Energy Resources Limited and Murphy Oil Company Ltd. v. Flint Engineering and Construction Ltd. (1984), 51 A.R. 42 (Q.B.); Nissan Automobile Co. (Canada) Ltd. v. The Continental Shipper, [1974] 1 F.C. 88 (T.D.); John Maryon International Limited et al. v. New Brunswick Telephone Co., Ltd. (1982), 43 N.B.R. (2d) 469; 141 D.L.R. (3d) 193; 113 A.P.R. 469; 24 CCLT 146 (C.A.); Irvington Holdings Ltd. v. Black et al. and two other actions (1987), 58 O.R. (2d) 449 (C.A.); Davie Ship building Limited v. The Queen, [1984] 1 F.C. 461; 4 D.L.R. (4th) 546; 53 N.R. 50 (C.A.).
AUTHORS CITED
Linden, Allen M. Canadian Tort Law, 4th ed. Toronto: Butterworths, 1988.
McGregor, H. McGregor on Damages, 14th ed. London: Sweet & Maxwell Ltd., 1980.
Sopinka, John and Lederman, Sidney N. The Law of
Evidence in Civil Cases. Toronto: Butterworths, 1974. Waddams, S. M. The Law of Damages. Toronto: Canada
Law Book Ltd., 1983.
Wigmore on Evidence, vol. 2, rev. by James H. Chad- bourn. Boston: Little, Brown and Co., 1979.
COUNSEL:
Nigel H. Frawley and Robert Shapiro for plaintiffs.
John T. Morin, Q.C. and Christopher J. Giaschi for defendants.
SOLICITORS:
McMaster Meighen, Toronto, for plaintiffs.
Campbell, Godfrey & Lewtas, Toronto, for defendants.
The following are the reasons for judgment rendered in English by
MCNAIR J .:
I. Questions Concerning Liability and Appor tionment of Fault
The plaintiffs' action is for damages resulting from the fracture of a segment of their submerged natural gas pipeline in Long Point Bay at the easternmost end of Lake Erie, alleged to have been caused by the dragging anchor of the defendant ship. The parties are agreed as to quantum for both the costs of temporary repairs and permanent
repairs to the damaged pipeline as well as the actual costs incurred by the plaintiffs in laying a new, relocated pipeline, but without any admission as to liability therefor. The general damages claim of the plaintiffs for business interruption and consequential loss of sales and profit is hotly con tested. The defendants deny negligence on their part and raise the defence that the damage com plained of was solely attributable to the plaintiffs' negligence in laying their pipelines in a known anchorage area at their own risk and in failing to properly protect them and to adequately mark their location. Alternatively, the defendants plead contributory negligence and the provisions of the Negligence Act, R.S.O. 1980, c. 315.
The parties filed an agreed statement of facts, the substantive portions of which read as follows:
1. The plaintiffs own and operate a natural gas field in Long Point Bay, Lake Erie, which feeds natural gas by submerged pipelines into the Consumers Gas land pipeline via the plain tiffs' compressor station at Port Maitland, Ontario and into the Union Gas land pipeline via their compressor station at Nan- ticoke, Ontario.
2. The plaintiffs' pipelines are laid on the bottom of Long Point Bay and were not buried when laid or otherwise protected. The plaintiffs' well heads extend approximately 5 feet above the lake bottom and are likewise not buried or protected except for wells within the designated trawling area where they are set below lake bottom and enclosed within caissons.
3. The defendant ULS International Inc. owns and operates the defendant ship "CANADIAN HUNTER", a bulk carrier of 18,192.33 gross tons and 730 feet in length overall, which lay at anchor in Long Point Bay from December 23 to December 25, 1983 loaded with a cargo of wheat. The anchors of the "CANADIAN HUNTER" weigh approximately 5 1 / 2 tons each. Her Master was Captain Sidney Van Wyck.
4. During the period from December 22 to December 25, 1983, nine vessels including the defendant vessel "CANADIAN HUNT ER" took shelter in Long Point Bay from severe wind and wave conditions in Lake Erie. The entry and departure times of each vessel are set out in Appendix "A" hereto.
5. Long Point Bay is a traditional and recognized anchorage area routinely used by ships of all sizes during poor weather conditions on Lake Erie. It is the only sheltered anchorage area in the eastern end of Lake Erie. Notwithstanding the existence of pipelines and wells on the bottom of Long Point Bay, it was
not in December 1983, declared as a designated prohibited anchorage area.
6. On December 24, 1983, at approximately 10:45 a.m., a section of the plaintiffs' pipeline was fractured. The likely cause of the fracture was a ship's anchor fouling the pipeline.
7. On December 24, 1983, both the "CANADIAN HUNTER" and the "LAKETON" (formerly the "LAKE NIPIGON") are known to have dragged their anchors along the bottom of Long Point Bay.
8. During the period from December 24, 1983 to January 1, 1984, a quantity of gas was lost to the atmosphere because of the fracture. By January 1, 1984, all of the affected wells had been shut in and the loss of gas was stopped.
9. The plaintiffs made temporary repairs to the pipeline at a cost of $186,956.25. The temporary repairs were completed by April 3, 1984. All of the affected wells were brought back into full production by April 5, 1984.
10. Rather than make permanent repairs, the plaintiffs elected to lay a new pipeline elsewhere in Long Point Bay. The estimated cost of permanent repairs to the fractured pipeline is $114,618.26. The new pipeline cost the plaintiffs $636,523.81.
11. Apart from gas lost to the atmosphere between the time of fracture and January 1, 1984 when the main line valve at junction 14 was shut, the amount of recoverable gas from the affected wells would only be reduced by a negligible amount.
The plaintiffs' natural gas field in Long Point Bay, Lake Erie, consisted at the material time of a network of 151 active wells supplying natural gas through an interconnected system of submerged pipelines to the plaintiffs' two customers, Consum ers Gas Company and Union Gas Limited, through the plaintiffs' compressor stations at Port Maitland and Nanticoke respectively. The Nan- ticoke facility did not come into operation until December 21, 1983. Prior to that, all gas produced by the network of wells was pumped through the compressor station at Port Maitland and sold to Consumers Gas Company. The plaintiffs have con tracts with their customers for the sale and deliv ery of natural gas. The plaintiffs' rights to explore for and produce natural gas from their field and to lay pipelines over the bed of Long Point Bay are dependant on natural gas production leases from the Crown in right of Ontario of the various lake bed parcels encompassing the entire area under lease, for which they pay an annual rental plus yearly royalties on the quantity of natural gas marketed. The submerged pipeline that suffered the fracture from a ship's anchor is the plaintiffs' inner bay line, so called, running from east to west for a length of about seven miles from the connec tion with the main line to Port Maitland at Junc-
tion 14 to the Nanticoke line at its westerly extremity. The inner bay line passes on its way through Junctions 16, 17, 18 and 19, and is located approximately 3.5 nautical miles to the north of the lighthouse at the entrance to Long Point Bay.
Pembina Exploration Co. Ltd., which is a whol- ly-owned subsidiary of Pembina Resources Lim ited, is the lessee under the production leases from the Crown and the active operator of the gas field facilities. Pembina, either directly or through its leasing agent, Elexco, provides up-to-date informa tion showing the location of its wells and junctions and interconnecting pipelines to the Canadian Hydrographic Service as well as to the Canadian Coast Guard Division of the Department of Trans port. As a result, marine navigational charts are continually updated and revised by these govern mental agencies, which also publish and circulate to the shipping industry and other interested par ties Notices to Mariners showing the location of the gas field facilities in the Long Point Bay area of Lake Erie and warning of the need for caution. Exhibit P-3, which is the navigational chart 2110 dated July 8, 1983 showing the respective locations of the nine ships anchoring in Long Point Bay over the period from December 22 to December 25, 1983, displays, inter alia, the following warning caution:
Gas pipelines and wells contain natural gas under pressure and damage to these installations would create an immediate fire hazard. Vessels anchoring in Lake Erie should do so with caution after noting the underwater positions of all gas wells, pipelines, submerged cables and other installations.
Gas well heads protrude to a height of up to 5 feet from the bottom and are marked by buoys.
Similar cautions were noted on the navigational charts used at the time of the mishap in question by Captain Gordon Stogdale, of the Canadian Coast Guard vessel Griffin, and Captain Sidney W. Van Wyck, master of the defendant ship Canadian Hunter, being Exhibits P-20 and P-24 respectively. Exhibit P-20 is an updated version of navigational chart 2110, corrected through
Notices to Mariners to the date of October 14, 1983, whereas Exhibit P-24 is the Canadian Hunter's version of the same chart similarly cor rected, but only to the date of December 4, 1981. The chart used by the master of the Griffin, unlike its earlier counterpart of December 4, 1981, gave a more graphic warning of the existence of gas well heads and pipelines by depicting their general location in grey-coloured, screened areas so as to serve as a better visual aid to the wary mariner.
There were further warnings of the marine haz ards occasioned by the exploitation of natural gas from the bottom of Lake Erie. A standard publica tion entitled Sailing Directions for Lake Erie, in a chapter devoted to the area of Lake Erie between Long Point and Point Pelee, warned mariners to be cautious about anchoring in this area because of submerged gas well heads and pipelines. In addi tion, the Notices to Mariners put out by the Canadian Coast Guard contained the following warning regarding the dearth of anchorage areas in Lake Erie:
Mariners are warned that no anchorage areas have been estab lished because of the existence of natural gas exploitation facilities on the bottom. The locations of these areas have been described in the weekly Notices to Mariners published by the Canadian Coast Guard.
Damage to facilities can be extremely hazardous because the pressurized natural gas contains toxic chemicals and is flammable.
Included among the nine ships seeking refuge in Long Point Bay from the storm on Lake Erie were the Canadian Coast Guard vessel Griffin, the Laketon (formerly the Lake Nipigon) and the defendant's bulk carrier Canadian Hunter, which was fully loaded with a cargo of wheat. The Canadian Hunter anchored at 11:56 hours on December 23 and weighed anchor and departed at 12:38 hours on December 25. This ship anchored at the spot indicated by a circle on its own naviga tional chart (Exhibit P-24) and marked with an "X" on Exhibit P-3. The water depth here was 141 feet and the anchorage position was relatively exposed to the elements. The Canadian Hunter was the only ship anchored to the south of the inner bay line. The Griffin arrived later at 18:40 hours on December 23 and anchored a consider-
able distance northeasterly of the Canadian Hunter at the point indicated by an "X" on its chart, and shown as well on Exhibit P-3. The Griffin left on an ice-breaking mission at 03:58 hours on December 24. The Laketon arrived at 06:05 hours on December 23 and departed at 01:05 hours on December 25. Its anchorage posi tion was the most northerly of all the vessels. Both the Laketon and the Canadian Hunter dragged their anchors during the period they were in Long Point Bay. The evidence is that the Laketon dragged anchor in a northeasterly direction for approximately a quarter of a mile, following which the anchor was raised and the vessel was brought back under power and re-anchored in approxi mately the same position.
The weather over Lake Erie during the period from December 23 to December 25, 1983 was generally foul. The wind was blowing from a west southwesterly quarter toward the northeast at a gale force of thirty to forty knots, causing high waves and heavy seas. It was snowing intermittent ly and there were patches of "steam" or low-lying fog over the water. Visibility was relatively poor. By December 25, the wind force had abated some what and visibility conditions had improved.
It is agreed that the pipeline was fractured at approximately 10:45 a.m. on December 24, 1983 and that fouling by a ship's anchor was the likely cause. The first intimation of this was a sudden drop in pressure at the Nanticoke compressor sta tion, which occurred in the forenoon of December 24, 1983. Mr. Robert Simpson, the superintendent of operations for Pembina Exploration Co. Ltd., was alerted to the problem by a phone call to the station operator at approximately 2:30 p.m. in response to a signal on his pager. Mr. Simpson kept an accurate chronology of subsequent events. The suspected causes were a freeze-up, colloquial ly termed a "hydrate", or a break in the pipeline. Methanol was pumped into the system to clear any possible hydrate, with negative results. A drop in pressure at Port Maitland confirmed the existence of a pipeline fracture. Diving boats were called in aid. A helicopter inspection on December 29 detected gas bubbles in the areas of Junctions 17, 18 and 19 on the inner bay line. Dive boats were
dispatched to the scene on the same day and a number of portions of the line were shut in, includ ing the main line valve at Junction 19. The gas bubbles still persisted at Junction 17. On January 1, 1984 the divers were finally able to shut in the main line valve at Junction 14, thereby preventing any further escape of gas into the atmosphere, and bringing the Port Maitland line back into full production. The divers then set about the task of effecting makeshift repairs to the inner bay line by connecting the fractured segments of the line with temporary hoses. This repair work was made more difficult, and indeed completely thwarted on a number of occasions, by heavy sea and ice conditions.
There were three fractures to the inner bay line, one at the original point of snagging about 15,000 feet or so westerly of Junction 17, another at Junction 18 and the last at Junction 19. The evidence is relatively uncontested that the fluke of a dragging ship's anchor snagged the pipeline at the first mentioned point to the west of Junction 17 and, by a combination of horizontal and verti cal movement, set up a chain of forces causing the line to break at three places. The first fracture occurred at Junction 18, followed by the one at Junction 19, with the final fracture occurring at the initial point of contact near Junction 17. The repairs to Junctions 19 and 18 were completed by February 21, 1984 resulting in a limited supply of gas being fed to the Nanticoke compressor station. Problems still continued to be encountered at Junction 17, one being a faulty coupling supplied by a manufacturer. Another was the freeze-up of the valve at Junction 17. Weather and ice condi tions intervened to delay further diving operations at the site. As a result of this combination of factors, repairs to Junction 17 were not completed until on or about April 3, 1984, when the valves were turned on. According to Mr. Simpson's evi dence, the Nanticoke line did not come back to full production until April 5, 1984. The defendants argue that the temporary repairs to the three fractured portions of the inner bay line were, or should have been, substantially completed within
the sixty-day period from December 24, 1983 to February 21, 1984.
The plaintiffs' case on the issue of legal liability for the damage complained of is simply that those responsible for the management and operation of the defendants' ship Canadian Hunter were at fault in anchoring their vessel where they did, having regard to existing conditions and the hazard posed by the nearby presence of a sub merged gas pipeline, and in permitting the ship to drag its port anchor for a distance of approximate ly a mile and a half without making any effort to run up the engines and regain their original anchorage position.
The defendants meet this case by pleading voluntary assumption of risk on the part of the plaintiffs and, as noted, contributory negligence. The point is made that Long Point Bay has been recognized and used for many years as a tradition al anchorage area for vessels seeking refuge from storms over Lake Erie and that the plaintiffs' gas wells and pipelines were developed and laid in such a way as to constitute obstacles and hazards to safe navigation. The argument is pressed that the methods chosen by the plaintiffs for the explora tion and development of the gas field failed to take any cognizance of the probability of damage to the submerged pipelines. The defendants point to the fact that no studies were made by the plaintiffs regarding the feasibility of re-routing or burying the pipelines as reasonable safeguards against damage from ships' anchors. The alternative objection was raised that the plaintiffs failed to adequately mark the location of gas well heads and pipelines with spar buoys or other appropriate navigational aids. Defendants' counsel excoriates the laissez-faire attitude of Pembina vis-à-vis its pipelines. Indeed, the main thrust of the defen dants' case on the liability issue is encapsulated in the following submission of their counsel:
Surely ... a company operating this sort of a system, with a highly flammable product running through it, under high pres sure, with the potential hazards that the company is well aware of, has a higher responsibility to the world at large and certainly to other people using the bay, than the one that seems to have been adopted by the company.
It is not good enough to simply say, well, we put down the lines and we tell the Hydrographic Services and we hope you find out about it, and if you do damage, we are going to sue you.
I will now review some of the legal principles applicable to the facts of the present case.
Permitting a ship to drag anchor so as to come into collision or become entangled with someone else's property and cause damage thereto is prima facie evidence of negligence in the absence of a reasonable explanation or proof of exonerating circumstances: Exeter City v. Sea Serpent (1922), 12 Ll. L. Rep. 423 (Adm. Div.); The Brabant (1938), 60 Ll. L. Rep. 323 (Adm. Div.); The Boltenhof (1938), 62 Ll. L. Rep. 235 (Adm. Div.); The Velox, [1955] 1 Lloyd's Rep. 376 (Adm. Div.); The Gerda Toft, [1953] 2 Lloyd's Rep. 249 (Adm. Div.); and Canadian Brine Ltd. v. The Ship Scott Misener and Her Owners, [1962] Ex.C.R. 441. Moreover, culpable want of knowledge of an apparent danger arising from a failure to utilize the means of knowledge at one's command can amount to negligence: The Mar- Tirenno, infra; and Submarine Telegraph Company v. Dickson (1864), 15 C.B. (N.S.) 760; 143 E.R. 983 (C.P.D.).
In The Boltenhof, supra, Bucknill J. considered the steps which the dragging ship should have reasonably taken and concluded at page 240:
In my view the Marklyn negligently failed to keep a careful watch, negligently failed to put down a second anchor or to pay out more chain on the anchor in use, and negligently failed to use her engines to ease the strain in due and proper time.
In The Velox, supra, Willmer J. said at page 382:
Even if it could be said that the Velox was not to blame for dragging her anchors in the first instance, nevertheless the situation called for a look-out of the utmost vigilance. In pursuance of her duty in that respect, the Velox ought to have been quick to appreciate that she was dragging, and, having discovered that she was dragging, she ought to have been quick to take steps to arrest her dragging, particularly in view of the fact that, to the knowledge of those on board her, there were
other vessels lying to leeward of her, vessels which, for all that was known, might very well be having their own difficulties in the weather conditions prevailing.
In those circumstances, it seems to me that, although the measures demanded by the situation may be regarded as exceptional, nevertheless they were no more than those required of a seaman of ordinary care and skill, having regard to the exceptional weather conditions prevailing.
Plaintiffs' counsel places much reliance on the case of Bell Telephone Co. v. The Mar-Tirenno, [1974] 1 F.C. 294; 52 D.L.R. (3d) 702 (T.D.); affd [1976] 1 F.C. 539; 71 D.L.R. (3d) 608 (C.A.), where a ship broke away from an exposed wharf from the combined forces of tide and ice to which the captain had been alerted. The captain was forced to drop anchor to avert colliding with a shoreside restaurant in a prohibited anchoring area of the St. Lawrence River occupied by the plain tiff's underwater telephone cable, thereby fouling and damaging the same. The Trial Judge rejected the pleas of inevitable accident and contributory negligence and found the defendant ship solely liable on the ground that the breaking away which caused the accident and the damage resulting therefrom were both clearly foreseeable. Addy J. stated the underlying rationale for the decision at page 300:
The case, in my view, therefore, turns on whether there was any negligence on the part of the captain or any member of his crew in tying up to that wharf in the first place, or in the manner in which the ship was secured or remained there, or in remaining there at all, and finally, whether he and his crew took all precautions, which normally should be taken to avoid the ship breaking away from its moorings as it did, including constant and proper observation of all conditions which might affect the security of the ship.
Where a person has actual dominion and control over an object or has a legal duty to control it and that object goes out of control and causes damage, then, it is obviously up to the person in control to explain by positive evidence the reason why the object went out of control or, at least, to establish by positive evidence that it was not due to any act or omission on his part or on the part of any other person whose actions were under his control.
The learned Judge drew the following conclusion at page 302:
The tying-up at the wharf in question, without informing himself fully, or, at least, taking all reasonable steps to inform himself fully of the nature and extent of the danger and, more specifically, of the very great force which the ice would exert on
a ship on a rising tide at that particular wharf, constituted negligence on the part of the captain.
The Ship Peterborough v. Bell Telephone Co. of Canada, [1952] Ex.C.R. 462; [1952] 4 D.L.R. 699, is instructive on the matter of contributory negligence in a case where the appellant's ship dropped anchor in a no-anchorage area of the St. Lawrence River and fouled and damaged the respondent's submarine cable, for which the appel lant was held solely liable in damages. The respondent was granted permission under the Navigable Waters Protection Act [R.S.C. 1952, c. 193] to lay the cable, subject to securing an ease- ment from the National Harbours Board. The easement was obtained. The evidence did not sup port a finding that the cable constituted an obstruction to navigation. The Court dismissed the appeal and affirmed the judgment of the Trial Judge. On the issue of contributory negligence, Cameron J. said at page 473:
In my opinion, there was no duty cast upon the respondent company when laying the cable in a no-anchorage area (where damage by ships' anchors would not normally be anticipated) to lay it at such length and in such a manner as to be able to withstand all strains and stresses to which it might be subjected by a ship's anchor which had fouled it, or in such a way that it could not be fouled by a ship's anchor. Here the cable was subjected to very great strain for perhaps three quarters of an hour while the vessel made attempts to release its anchor, and the further strain of raising it to the surface. ...I agree with the opinion of the trial Judge that it is impossible to find that the cable was laid or maintained in such a way as to have con tributed to the accident or the resulting damage.
In Assiniboine (School Division of) South No. 3 v. Hoffer et al. (1971), 21 D.L.R. (3d) 608; [1971] 4 W.W.R. 746 (Man. C.A.), a snowmobile owned by the adult defendant went out of control, while being operated by his infant son, and struck and fractured an unprotected gas-riser pipe provid ing a public school building with natural gas. The pipe had been installed by the corporate defend ant, a public utility company. Gas under pressure escaped into the boiler room of the school and exploded, causing a fire and extensive damage to the school premises. Damages were apportioned at trial on the basis of 50% to the owner and operator of the snowmobile and 50% to the gas company. Both parties appealed the decision. Dickson J.A. (as he then was), delivering the judgment of the
Court, dealt with the issue of the liability of the gas company at pages 615-616 D.L.R., as follows:
I am also of the opinion that Greater Winnipeg Gas Co. Ltd. is liable to the plaintiff on the ground that the installation of the gas service was negligently constructed in the sense that it was constructed in such place and manner as to make likely the type of damage which ensued. The gas company was respon sible for the construction of the service line leading from the street, the service riser, and attached equipment and meter. It is difficult to conceive of any person, conscious of the explosive properties of natural gas, designing and installing a service so patently dangerous. Gas escaping from any fracture of the pipe below the regulator would assuredly find its way into the boiler room. The gas company ought to have reasonably foreseen damage to the gas-riser pipe. It is true that persons are not bound to take extravagant precautions but they must weigh the probability of injury resulting and the probable seriousness of the injury. Although the probability of the gas-riser pipe being struck by an automobile, a motorcycle or an auto-toboggan was not great, the pipe being tucked into the corner of the building, the probable seriousness of any injury was very great. Against this must be weighed the cost and difficulty of the precautions which could have been taken. Protective pipes could have been installed at small cost and little difficulty. The duty to take protective measures increases in direct proportion to the risk. In these circumstances, the gas company failed to exercise reason able care where there was a duty to exercise a high degree of care.
In Heeney v. Best et al. (1979), 28 O.R. (2d) 71; 108 D.L.R. (3d) 366; 11 CCLT 66 (C.A.), the defendants negligently drove their truck into an overhead hydro line, interrupting the flow of elec trical power to the plaintiff's premises and extin guishing the supply of oxygen to his chicken barns, with the result that most of the chicks died from lack of ventilation. The plaintiff had a power failure alarm device, which could have alerted him to the power failure and enabled him to save the chickens, but it was not plugged in on the night in question. The Trial Judge found the plaintiff to be 50% at fault. The plaintiff appealed this finding to the Ontario Court of Appeal, which held that the appellant should recover 75% of his damages. MacKinnon A.C.J.O., writing the opinion of the Court, was clearly of the view that the greater fault was that of the respondent who had caused
the power interruption, leading him to conclude at page 76 O.R.:
The appellant's negligence only contributed to the damages he suffered, the respondent being wholly to blame for the negligent act which set in train the events that caused the ultimate injury or damage to the appellant. Under the circum stances, I assess the degree of fault or negligence of the appellant at 25% and of the respondent at 75%.
The evidence is conclusive that the Canadian Hunter was the only vessel anchored at the ma terial time in a position southerly and to windward of the inner bay line and less than one nautical mile therefrom. In my view, prudent seamanship would seem to dictate a better choice of location.
The only firsthand explanation of why the cap tain of the Canadian Hunter came to choose this particular place of anchorage is contained in the excerpts of the examination for discovery of Cap tain Sidney W. Van Wyck, which were read into the record by plaintiffs' counsel. His discovery evidence relating to the actual anchorage position reads as follows:
300 MR. FRAWLEY: Q. Captain, any particular reason why you chose that location to anchor in?
A. It would be a safe spot and the number of ships that were in the Bay. I didn't see any more room.
301 Q. I see. Before you anchored, did you go in further to have a look or did you just go straight up to that—
A. Well I went straight up, as I said. This is where I ended up.
302 Q. Yes, right.
A. This was my position when she settled down.
303 Q. So you didn't go further in the Bay to have a look?
A. No.
This explanation belies the fact that the vessel closest to the Canadian Hunter at the time was the Canadian Century, which was lying at anchor in a relatively large and unobstructed area of the bay on the northerly side of the inner bay line and about four nautical miles to the northwest of the Canadian Hunter's position. The Canadian Coast Guard vessel Griffin came in later that evening and anchored in the same general area about a mile to the south of the Canadian Century. I find
as a fact that there was nothing which could have prevented the Canadian Hunter from anchoring where the Griffin did later that same evening. Indeed, the defendants' own expert witness in rebuttal, Captain John MacDonald, agreed on cross-examination that it was possible for two or more ships to anchor in the area where the Canadian Century and the Griffin were anchored. Nonetheless, Captain MacDonald clung to the view that there was nothing wrong with the anchorage position chosen by the captain of the Canadian Hunter. Suffice it to say, I do not accept that conclusion.
The expert witness retained by the plaintiffs to give opinion evidence on the circumstances sur rounding the mishap, Captain William R. Barr, was clearly of the opinion that the captain of the Canadian Hunter "ought to have anchored further to the north and inside the bay where there would be less water underneath the ship and where it afforded greater protection". He also deplored the fact that the captain anchored in an exposed posi tion and at a water depth for which he had insuffi cient anchor cable to safely hold the vessel, given the weather conditions prevailing at the time. Apart from the poor choice of anchor location, Captain Barr was also critical of the apparent disregard of the nearby gas pipeline on the part of those responsible for the operation of the Canadi- an Hunter, and their navigation and record keep ing generally. The bottom line conclusion was that the master of the vessel and those for whom he was responsible acted imprudently in the circum stances. I accept the conclusions of Captain Barr in preference to those of Captain MacDonald, where they differ.
Counsel for the plaintiffs urges that an adverse inference should be drawn from the defendants' failure to call Captain Van Wyck or any of his officers or crew members to explain a number of crucial questions left unanswered. He cites the following examples: why was the vessel anchored to the south and less than a mile to windward of the inner bay line; did anyone pay any attention to the navigational charts and other update literature pointing to the presence of submerged gas well heads and pipelines; were there any ice pole buoys marking the presence of the inner bay line; why
did the captain of the Canadian Hunter not anchor in the area where the Griffin afterwards anchored; and, finally, why did the captain permit his vessel to drag its anchor for a mile and a half without taking any corrective measures? Defendants' coun sel stated quite frankly that he made the decision not to call the master of the Canadian Hunter as a witness at the trial, based on his opinion that all the essential evidence was before the Court by way of the agreed statement of facts, the discovery evidence of Captain Van Wyck, the supporting charts and log books and the evidence given by the plaintiffs' expert, Captain Barr. For a useful com mentary on the principles relating to the drawing of adverse inferences, see: Sopinka and Lederman, The Law of Evidence in Civil Cases (Butter- worths, 1974) pages 535-537; Wigmore on Evi dence, vol. 2, paras. 285, 286, 289; and Northern Wood Preservers Ltd. v. Hall Corp. (Shipping) 1969 Ltd. et al., [1972] 3 O.R. 751; (1972), 29 D.L.R. (3d) 413 (H.C.); affd (1973), 2 O.R. (2d) 335; 42 D.L.R. (3d) 679 (C.A.). In view of the explanation given by defendants' counsel, I am not prepared to draw an adverse inference based simply on the bare fact that Captain Van Wyck and others associated with the navigation of the Canadian Hunter were not produced as witnesses. However, I agree with counsel for the plaintiffs that the absence of any explanation of facts which tell against a party supports the drawing of an adverse inference against that party, once a prima facie case has been established by his opponent. I prefer to treat the matter on that basis.
As previously indicated, the navigational chart kept aboard the Canadian Hunter was updated only to December 4, 1981. Why was it that the Canadian Hunter did not have on board at the time the current edition of navigational chart 2110 dated October 14, 1983 (Exhibit P-20), which gave a much better visual warning of the hazards posed by the submerged well heads and pipelines than the earlier edition? I am in complete agree-
ment with the opinion expressed by Addy J. in The Mar-Tirenno, supra, where he said at page 301:
In the same way that failure to consult a chart constitutes negligence, ... failure to have up-to-date charts aboard would equally constitute negligence.
I accept the evidence of the plaintiffs' expert, Mr. Hluchan, that the damage to the plaintiffs' pipeline was attributable to an anchor snag by a vessel of a size comparable to that of the Canadian Hunter and his explanation of the sequence of fracturing caused by the anchor dragging in a north to northeasterly direction. I am inclined, however, to discount his speculative "slight possi bility" that the damage at Junction 18 of the inner bay line could have been caused by a second vessel, which begs the consequent argument of defen dants' counsel that the Coast Guard vessel Griffin was a likely candidate for this eventuality. The Griffin was anchored well to the north of the inner bay line and the weight of evidence is totally against any finding of involvement on its part.
I find on the evidence in its entirety that the Canadian Hunter was the only vessel poised, as it were, to snag the plaintiffs' pipeline with its drag ging anchor at a point to the west of Junction 17 in the inner bay line and that it did in fact do so, thereby causing the three resulting fractures which occurred in the manner and sequence described by the plaintiffs' expert, Mr. Hluchan.
I also find that the master of the Canadian Hunter, Captain Van Wyck, was negligent in the following respects, namely: (1) in choosing the place of anchorage he did under the circum stances; (2) in permitting his vessel to drag its anchor for a mile and a half without taking any corrective measures; (3) in failing to have aboard the most up-to-date navigational charts available; and (4) in failing to check his ship's position regularly. In sum, Captain Van Wyck failed in his duty to exercise the requisite degree of careful and prudent seamanship that the occasion demanded. In my opinion, there can be little doubt that the captain of the Canadian Hunter was "certainly asking for trouble" in choosing to anchor where he
did in the sense that he ought to have reasonably foreseen the probable likelihood of the ultimate injury which occurred.
The plaintiffs inherited the pipeline system, including the inner bay line, in its present form when they purchased the gas field from Anschutz (Canada) Exploration Limited on August 1, 1980. The evidence is that the plaintiffs and their prede cessor had generally complied with the statutory and regulatory enactments pertaining to gas pipe line systems. For instance, Anschutz had obtained the approval of the Minister of Transport for its gas pipeline system and an exemption from the application of subsection 5(1) of the Navigable Waters Protection Act [R.S.C. 1970, c. N-19] and the regulations thereunder. The one exception to the regime of general statutory compliance seems to have been CSA Standard Z184-M1979, which was made applicable to the operation and mainte nance of gas pipelines systems by section 2 of O. Reg. 629/80 enacted under The Energy Act, 1971 [S.O. 1971, c. 44] and filed on August 1, 1980. Section 6.4.2 of the Standard deals with the topic of pipeline protection and suggests additional burial as one means of protecting offshore pipe lines from accidental damage by vessel activities, including anchoring and fishing operations. Inci dentally, the applicability of the CSA Standard to offshore pipelines was removed afterwards by O. Reg. 450/84 filed on July 13, 1984. Apart from its relative innocuousness, it seems to me that nothing significant turns on whether section 6.4.2 of the CSA Standard applies or not by reason that the civil consequences of a breach of statutory duty are subsumed in the law of negligence: R. in right of Canada v. Saskatchewan Wheat Pool, [1983] 1 S.C.R. 205; 143 D.L.R. (3d) 9; [1983] 3 W.W.R. 97; 23 CCLT 121; 45 N.R. 425.
The main point of the defendants' argument is that the risk of pipeline damage from ships' anchors was something that was reasonably fore seeable and that the burying of the six-inch pipe lines or marking the same by spar buoys would have avoided or substantially minimized this risk.
Plaintiffs' counsel counters this by asking how could they be expected to know where a pipeline fracture was likely to occur, and by pointing out as well that the costs of burying the pipeline would be astronomic. Plaintiffs' counsel also makes the point that the trenching of the pipelines to the depth of two metres or six feet suggested by the defendants' expert on protective methods for sub- sea pipelines, Norman I. Hanson, would create insurmountable problems for the divers in making necessary repairs.
Mr. Hanson's report and his viva voce evidence in support generally favour trenching as a means of protecting submerged gas pipelines, although he frankly admitted that he had given no consider ation to the economic factors involved in such an enterprise. He cited several reported instances where pipelines had been buried in other places in Canada. Much of his evidence focused on the CSA Standard, to which I have already alluded. Mr. Hanson was strongly of the opinion that the fluke of an anchor of the size and weight of the ones employed by the Canadian Hunter would dig into the clay bottom of Lake Erie to a depth of forty inches. This led him to conclude that the safety margin of trenching to avoid damage from an anchor of that size would be two metres or six feet. He was extensively cross-examined on the litera ture search abstracts contained in Appendix B of his report relating to the trenching of sub-sea pipelines in other jurisdictions and particularly the conclusion reached in the appended North Sea survey that trenching and burial of pipelines "do not offer any real protection against anchors from larger ships". The full, unexpurgated edition of the North Sea survey was entered as Exhibit D-18 during the course of Mr. Hanson's cross-examina tion. In my view, it is unnecessary to elucidate its conclusions any further than to repeat what appears to be the final conclusion of its author, John Strating, where he says:
Presently there appears to be no justification for trenching and/or burying a large diameter pipeline for reasons other than
on-bottom stability. In areas with significant fishing activities, the pipeline should be provided with a high quality concrete coating.
I accept Mr. Hanson's conclusion that the inner bay line would have had to have been buried to a depth of two metres to achieve a safe margin of protection from a ship's anchor of the size of the Canadian Hunter's. Obviously, this measure of protection could only have been accomplished at great cost. In my opinion, the burying of the inner bay line was not a reasonable and viable means of avoiding the foreseeable risk of injury by a ship's anchor.
The question that remains to be considered is whether the plaintiffs were at fault by failing to take the reasonable precaution of marking the inner bay line with metal spar buoys of a type that would be discernible by ships' radar. In other words, was this such an obvious omission on the part of the plaintiffs as to fall within their range of reasonable foreseeability as it existed prior to the date of the accident? In addressing this issue, I am precluded from taking into account any protective measures that may have been advocated or even introduced after the event in question. I am think ing here particularly of the proposal regarding pipeline incidents in Long Point Bay prepared by the gas producers and the Ministry of Natural Resources, the minutes of the meeting of the Coast Guard Advisory Council on May 2, 1984, and the letters written by Mr. Simpson, of Pembina, to P. A. Palonen, of the Ministry of Natural Resources, dated March 28 and June 22, 1984 respectively. Defendants' counsel seemed to set much store on this hindsight evidence but, in my view, it must be disregarded in determining whether liability should be fastened on the plaintiffs for having failed to mark the location of the inner bay line by appropriately spaced spar buoys. In short, I agree fully with the statement made by Dickson J.A. in the Assiniboine School case, supra, at page 618 D.L.R. where he said:
I agree that in general one must not take into account, in determining negligence, the fact that the defendant introduced
protective measures after the event. "People do not furnish evidence against themselves, simply by adopting a new plan in order to prevent the recurrence of an accident." But, with respect, I do not read the Judge's words as meaning what counsel alleges they mean. On the contrary, it seems to me that what the Judge is saying is that with the benefit of hindsight it is apparent that protective steps were taken after the event, but that it is his duty, as he sees it, to determine whether damage to the gas-riser pipe was reasonably foreseeable at the time of the accident in 1968, and prior thereto when the installation was made.
Mr. Simpson testified that they used wooden ice pole buoys to mark for their own convenience the location of existing gas well heads and pipeline junctions. I take it that these buoys were of the approved design required by subsection 27(13) of Regulation 752 [R.R.O. 1980] enacted under the Petroleum Resources Act [R.S.O. 1980, c. 377]. As for the inner bay line at the time of the accident, Mr. Simpson recalled that there were ice pole buoys marking Junctions 15, 18 and 19, but there was none at Junction 17 and he did not know about Junction 16. He explained that these ice pole buoys were not detectable by ships' radar and frankly acknowledged that they were not intended as navigational aids to the shipping industry. He also conceded that these buoys lacked flotation stability and had a tendency to tip over and lie flat from wave action so that they would not be clearly visible in heavy seas.
The evidence of the defendants' expert, Captain MacDonald, was to the effect that metal spar buoys with radar reflectors, spaced at regular intervals of 4,000 feet or so apart along the inner bay line, would have been of assistance to the master of a vessel in helping him to determine his position in relation to the pipeline. Captain Stog- dale, of the Griffin, agreed during his testimony that metal spar buoys, regularly interspersed at well heads and pipeline junctions, could serve as an aid to navigation, but with the qualification that too many would be likely to cause confusion. Cap tain MacDonald had entertained the same reserva tions about a "mass of buoys".
The question, as it seems to me, comes down to this: was the plaintiffs' failure to mark the location of the inner bay line by appropriately spaced and radar sensitive spar buoys a fault or omission that contributed to the damage complained of in the sense of being an effective cause thereof? In my opinion, it was not. In reaching this conclusion, I am mindful of the words of Macdonald J.A. in Rose et al. v. Sargent, [1949] 3 D.L.R. 688; [1949] 2 W.W.R. 66 (Alta. C.A.), where he said at page 693 D.L.R.:
It is not enough that there should be some fault on the part of the plaintiff without which the damage complained of would not have been sustained. Such negligence may be merely sine qua non. To constitute contributory negligence in the legal sense it must be established that the negligence charged was an effective cause of the damage.
I am further influenced by the following statement of Anglin C.J.C. in McLoughlin v. Long, [1927] S.C.R. 303; [1927] 2 D.L.R. 186, at page 310 S.C.R.:
In order to constitute contributory negligence it does not suffice that there should be some fault on the part of the plaintiff without which the injury that he complains of would not have been suffered; a cause which is merely a sine qua non is not adequate. As in the case of primary negligence charged against the defendant, there must be proof, or at least evidence from which it can reasonably be inferred, that the negligence charged was a proximate, in the sense of an effective, cause of such injury.
II. Assessment of Damages for Temporary and Permanent Repairs
It is common ground that the cost of temporary repairs to the inner bay line in the agreed amount of $186,956.25 is not in issue. Consequently, the plaintiffs are entitled to recover that amount as damages flowing from the injury.
What is very much in issue is whether the plaintiffs are also entitled to recover the cost of permanent repairs in the agreed quantum of $114,618.26 which, according to counsel for the defendants, were never carried out nor required to be carried out. Defendants' counsel argues forcibly that the moneys expended for temporary repairs achieved the goal of bringing the plaintiffs' busi ness undertaking back into full production, despite the plaintiffs' subsequent decision to abandon the original inner bay line and relocate it elsewhere at an agreed cost of $636,523.81. In his submission,
the plaintiffs should not be permitted to recover both the cost of temporary repairs and the estimat ed cost of permanent repairs because that would provide the plaintiffs with a compensatory windfall for repair costs which they never had to incur.
The argument of plaintiffs' counsel is simply that the estimated cost of permanent repairs repre sents damages which were clearly foreseeable as being likely to flow naturally from the fractured pipeline. He submits that the plaintiffs, for their own good reasons, decided to relocate the inner bay line elsewhere and spent a considerable sum of money in doing so, but this of itself should not permit the defendants to escape liability for dam ages based on the estimated cost of permanent repairs that were reasonably foreseeable in the circumstances. Plaintiffs' counsel further submits that the defendants should not be permitted to profit from the fact that the plaintiffs decided upon a different course of action following the accident.
In The London Corporation, [1935] P. 70 (C.A.), the plaintiffs' ship was not repaired but was sold to be broken up, after having been slight ly damaged in a collision with the defendants' vessel. The defendants agreed to the estimated cost of repairs, but no repairs were done. Consequently, the defendants contended that the plaintiffs had suffered no loss. Greer L.J. said at page 78:
... in cases of this sort, the prima facie damage is the cost of repair, and circumstances which are peculiar to the plaintiffs— namely, that they have, before the damage has been deter mined, sold the vessel to be broken up, is an accidental circum stance which ought not to be taken into account in the way of diminution of damages ....
This principle was applied in Fitzner v. MacNeil (1966), 58 D.L.R. (2d) 651 (N.S.S.C.), where the plaintiff was awarded damages in the full amount of a repair estimate for the damage done to his automobile as a result of the negligent driving of
the defendant, even though the authorization for such repairs had been revoked by the plaintiff.
The learned author of McGregor On Damages, 14th ed., makes the following statement in para graph 1001 at page 686:
The fact that the repairs have not yet been executed before the hearing of the action, or will never be executed at all, does not prevent the normal recovery. Since damages may on gener al principles be given for prospective loss, it is immaterial that the repairs are not yet executed.
In the present case, the parties are in agreement as to the quantum for the estimated cost of perma nent repairs. Thus, there can be no question about the reasonableness of the actual amount so agreed to. If I apprehend the matter correctly, the defen dants' argument turns on the point of whether damages are properly recoverable for the cost of permanent repairs that have not been, and never will be, executed. In my opinion, these permanent repairs must be characterized as a prospective loss which the defendants might reasonably have fore seen as a consequence of their negligence in frac turing the plaintiffs' pipeline. I find therefore that the defendants are accountable to the plaintiffs for the cost of permanent repairs in the agreed amount of $114,618.26.
III. Assessment of General Damages for Loss of Business Income
A. Time Frame for Assessment of General Damages
The next question concerns the appropriate time frame for the assessment of general damages for loss of business revenue pending the completion of temporary repairs to the inner bay line. Essential ly, the issue is simply whether such damages should be calculated in terms of the 60-day period from the date of fracture until February 21, 1984, or the 104-day period terminating on or about April 5, 1984. The problem arose from four faulty plidco couplings for connective hoses which had been incorrectly assembled by the supplier. The divers noticed the defective assembly and correctly reassembled three of the couplings, but for some reason did not reassemble the fourth. Two of the couplings were installed at Junction 19 and func-
tioned perfectly. The remaining two, one of which proved defective, were installed at Junction 17. When a pressure test was conducted at this Junc tion on February 23, 1984, the hose connection separated from the faulty plidco coupling. On February 24, the faulty coupling and hose connec tion were repaired and reinstalled. The pressure test was successful and there were no further leaks at this Junction. But that was not the end of the problem. The valve at Junction 17 had become frozen. Weather and ice conditions conspired to prevent the completion of repairs at Junction 17 until April 3, 1984, when the valves were turned on. I find on the evidence that full productive flow of gas through the Nanticoke line was not attained until April 5, 1984.
Counsel for the plaintiffs concedes that Pem- bina's inability to resume full production on Feb- ruary 23, 1984, was due to the failure of its divers to reassemble correctly all four of the faulty cou plings. He submits, however, that such failure either did not constitute negligence, being merely an understandable mistake made under adverse weather conditions, or represented negligence of such a low degree as not to be actionable. Plain tiffs' counsel further points out that the divers' omission resulted in only two days of lost produc tion, there being no evidence that the faulty cou pling had anything at all to do with the problems subsequently encountered at the Junction 17 valve.
Counsel for the defendants asserts that it was the intervening negligence of the plaintiffs which caused the delay in production beyond the date of February 21, 1984. He bases this submission on the evidence of the plaintiffs' diving supervisor, Mr. Petrochuk, arguing that the freeze-up of the valve at Junction 17 was attributable to the faulty plidco coupling. It follows, in his submission, that it was the plaintiffs' own negligence in installing this defective coupling which caused the postpone ment of production until April 5, 1984, and that
this intervening force absolves the defendants from liability.
Linden, Canadian Tort Law, 4th ed. (Toronto: Butterworths, 1988) had this to say of the modern version of the principle of intervening force at page 345:
There was once a time when a negligent actor could be insulated from liability for consequences brought about by an intervening force which came into operation after his act was complete. The true nature of the problem was clouded by phrases such as act us novus interveniens, the "last wrongdoer" and the everpresent discussion of causation. Today, however, it is clear that wrongdoers are not immune from responsibility in these circumstances.
No one could quarrel with that statement. Suffice it to say, however, that liability will still attach where the intervening act is one which ought rea sonably to have been foreseen by the original wrongdoer. This principle was expounded by Schroeder J.A. in Martin v. McNamara Construc tion Company Limited and Walcheske, [1955] O.R. 523; [1955] 3 D.L.R. 51 (C.A.), at page 527 O.R.:
I hold it to be an established principle that damage is recoverable if, despite the intervening negligence of a third party, the person guilty of the original negligence ought reason ably to have anticipated such subsequent intervening negligence and to have foreseen that if it occurred the result would be that his negligence would lead to loss or damage.
The principle thus elucidated by Schroeder J.A. was also quoted in Walls v. MacRae and Metro Fuels Co. Ltd. (1981), 36 N.B.R. (2d) 1; 94 A.P.R. 1 (Q.B.), a case relied on by the defendants and, in my view, is sufficiently applicable to the facts of the present case to enable me to dispose of this particular issue. In my judgment, the failure of the divers to reassemble correctly all four of the faulty plidco couplings did not constitute action able negligence in the circumstances. Irrespective of whether it was a mere mistake or a minor negligent act, I find on the whole of the evidence that it was an intervening force which the defen dants ought reasonably to have anticipated as being a likely consequence of their original negli gence. In the result, I am impelled to conclude that the defendants must be held accountable for any damage sustained up to the date of the resumption of full production on April 5, 1984. Moreover, I also find on the evidence in its entirety that the
plaintiffs took all reasonable steps to achieve full production by that date and that the 104-day period of lost production was not inordinately long under the circumstances.
B. Competing Theories of Business Interruption Loss
Expert reports estimating the loss of business income were prepared for the plaintiffs by Michael A. Copeland, of Coopers & Lybrand, and for the defendants by Donald R. Holmes, of Peat, Mar- wick, Mitchell & Co. Both experts testified and were extensively cross-examined at trial, and they both impressed me as competent and reliable char tered accountants. The two competing theories propounded by the rival experts to measure the plaintiffs' loss of income were not entirely dissimi lar, when reduced to their simplest form. Both experts arrived at an estimated value for the lost production over the 104-day period. Mr. Copeland adopted a cash flow approach to arrive at a net total loss claim of $572,226. This was premised on the assumption that the gas production lost during the period of interruption would not be made up, if at all, until the end of the life expectancy of the gas reserves, and that the net present value of any production received at that point in time would be negligible. Consequently, it was his view that the plaintiffs should be awarded the net amount of the current value of lost production in order to afford adequate compensation.
Mr. Holmes proceeded on the assumption that the reserves of natural gas did not decrease in volume after the wells were shut in, but rather remained available to be recovered in their entire ty, once production resumed. In other words, there was no permanent loss of natural gas. Mr. Holmes utilized overlay charts and graphs to support his theory that the shutting in of the wells for the period of 104 days, followed by the resumption of production, resulted in no reduction of the volume of gas, but simply effected a deferral of production for successive periods of 104 days over the twelve and a half year life of the gas field. In Mr. Holmes' view, all future revenues received by the plaintiffs from such deferred production, albeit
discounted to a present value, ought to be deduct ed from the plaintiffs' claim for the present value of lost production to avoid over-compensating them for their loss. The application of this methodology led Mr. Holmes to conclude that the estimated total loss of income to the plaintiffs would be in the range of $226,139 to $308,018.
C. Legal Arguments and the Applicable Law
There appear to be few Canadian authorities on business interruption claims of this nature. The plaintiffs rely heavily on Continental Oil Co. v. S S Electra, 431 F.2d 391 (5th Cir. 1970). This was a case where production from oil wells was sus pended for 130 days as a result of the defendants' vessel colliding with the plaintiffs' offshore drilling platform. The parties reached an agreement as to the physical damage to the platform, but were unable to agree on damages for suspension of production from the wells. That issue was submit ted to a commissioner, who concluded that the damages for loss of production were limited to interest on the $60,000 net production figure for 130 days. The District Court approved the amount so determined. The plaintiffs appealed and the defendants cross-appealed. The Court of Appeals upheld the appeal on the ground of error by the commissioner and the District Court, and awarded the appellants damages at 90% of $60,000 for the value of the net production. As the Court noted particularly at page 392:
The commissioner and the District Court erred. They focused on the fact that the oil companies had not shown that they had lost any oil as a result of the collision. As they viewed the matter, since the oil was still intact and available the plaintiffs ultimately could bring it to the surface and realize profit therefrom just as they would have during the 130 day period had they been operating—or at least they had not proved with reasonable certainty that this would not occur, so that their loss was purely theoretical. In this court the shipown- er continues to focus on the fact that plaintiffs have not lost oil as a capital asset and strenuously insists that to allow $60,000 as damages is to allow a double recovery.
The Court dealt with these errors and concluded as follows [at page 392]:
All of this wholly misses the mark. The oil companies do not claim for lost oil or damage to oil as an asset. Their suit is for damages suffered as a consequence of the collision of the ship with the platform. Profit on oil production is simply one means of measuring the damage suffered. The plaintiffs have lost the use of their capital investment in lease, platform and producing wells for 130 days during which that investment was tied up without return. The fact that the same amount of profit can be made at a later time with the same investment of capital by removing from the ground a like quantity of oil at the same site does not alter the fact that the plaintiffs are out of pocket a return on 130 days use of their investment. Presumably the oil companies ultimately will produce from the reservoir all the oil that is economic to produce, but, as the District Court pointed out, it will require 130 days longer to do so. The plaintiffs must stay on the site 130 days longer, with investment in place, than necessary but for the ship's negligence.
This is no theoretical, shadowy concept of loss. It is squarely within the basic damage doctrine for marine collision of restitutio in integrum, as applied in many comparable situa tions. Thus, for the vessel laid up for repairs:
In order to make full compensation and indemnity for what has been lost by the collision, restitutio in integrum, the owners of the injured vessel are entitled to recover for loss of her use, while laid up for repairs. When there is a market price for such use, that price is the test of the sum to be recovered. When there is no market price, evidence of the profits that she would have earned if not disabled is com petent; but from the gross freight must be deducted so much as would in ordinary cases be disbursed on account of her expenses in earning it; in no event can more than the net profits be recovered by way of damages; and the burden is upon the libellant to prove the extent of the damages actually sustained by him. [Emphasis added.]
The Court made the following observation at page 393:
The oil companies are like a single shipowner with his ship laid up. It would be no answer to his claim to assert that he has lost nothing because the same cargo is still on the dock when his ship comes out of repair and that he can move it then—if other cargoes are also then available.
The Continental Oil case has been followed in several United States decisions, namely, National Steel Corp. v. Great Lakes Towing Co., 574 F.2d 339 (6th Cir. 1978); and U. S. Oil of Louisiana,
Ltd. v. Louisiana Power & Light Co., 350 So. 2d 907 (La. Ct. App., 1st Cir. 1977), and has been mentioned in other cases. It was also mentioned in Canada in Total Petroleum (N.A.) Ltd. v. AMF Tuboscope Inc. (1987), 81 A.R. 321; 54 Alta. L.R. (2d) 13 (Q.B.), but only in reference to distin guishing for loss of profit as a reasonably foresee able result in the circumstances of that case from a claim for damages for loss or deferral of produc tion revenue, which was held to be too remote.
It is a well established principle that wrongful interference with profit-making property causing the owner to be deprived of the use thereof is compensable as damages for lost profits: Wad- dams, The Law of Damages (Canada Law Book Limited, 1983), paragraphs 192 and 203; and Pacific Elevators Ltd. v. Canadian Pacific Rail way Co., [1974] S.C.R. 803; (1973), 41 D.L.R. (3d) 608.
In Pacific Elevators Ltd., supra, unloading facilities at the plaintiffs grain elevators were damaged as a result of the derailment of railway cars on two separate occasions, both of which were attributable to the negligence of a railway employee. The plaintiffs actions for claims of $33,658 and $232,594 respectively were allowed in full at trial. The Court of Appeal reversed the trial decision and an appeal was taken to the Supreme Court of Canada. The Court allowed the appeal in part, but varied the judgment at trial by dismissing the first action and allowing the plaintiff a much lower damages recovery in the second action. Pigeon J., delivering the judgment of the Court, said at page 806:
Grain cars diverted are really the basis on which the claim is to be assessed because, as counsel for the railway pointed out, appellant's revenues and profits for 1966 were up from the previous year. Its inventory was up too, as well as the quantities of grain received, stored and shipped. No ship was diverted from its dock. This does not mean that it suffered no loss because if, without the disruption caused by the accidents, it would have been able to handle and store still more grain and consequently would have made higher profits, it is undoubtedly
entitled to claim the loss suffered although in spite of that loss, its profit was higher than in the immediately preceding year.
In my view, the Pacific Elevators case lends fur ther countenance to the principle that lost profits are a proper measure for determining compensable damages flowing from the loss of use of profit- making property.
Counsel for the defendants relies heavily on the case of Bolivar County Gravel Co., Inc. v. Thomas Marine Co., 585 F.2d 1306 (5th Cir. 1978), to support his argument that the U.S. Fifth Circuit Court of Appeals in Continental Oil did not decide that lost profits are the appropriate measure of damages in cases involving a shut-down of oil or gas wells. Defendants' counsel further relies on Norcen Energy Resources Limited and Murphy Oil Company Ltd. v. Flint Engineering and Con struction Ltd. (1984), 51 A.R. 42 (Q.B.), a case where the Alberta Court of Queen's Bench reduced the damages assessed for loss of produc tion from oil wells shut down as a result of fire damage to the plaintiffs' oil battery by the amount of $39,800 representing the present value to the plaintiffs of recovery of lost production over the life of the field. Medhurst J. offered no explana tion for the quantification and deduction of this present value item.
In the present case, the damages claim for busi ness interruption loss is based on the net sales value of the volume of production lost over the 104-day period. According to the defendants' theory, this is not the right approach because the oil was not lost irretrievably; rather, it is simply a case of the deferral of production. In my view, this argument is irrelevant because it belies the fact that even if the plaintiffs ultimately produce the full volume of untapped natural gas, they are still delayed for a period of 104 days in achieving that goal. Counsel for the plaintiffs stressed repeatedly that there is no certain likelihood that the shut-in gas will ever be produced and that its future recovery is only a possibility at best, and will have to await events. He summarizes his argument as follows:
... you have Mr. Copeland saying that the plaintiffs cannot use that 104 days worth of gas right now and it is a loss to them. There is no guaranty or no assurance that they are ever going to get that gas back again in the future. I would submit that there is some compelling logic to that because we have the evidence of Mr. Simpson that these wells have a life expectancy of 20 years. My clients have a 10-year lease. They have an option of renewing it for another 10 years. They may not wish to renew, the Crown may not wish to renew. The sale of gas may drop. My clients' fortunes may plummet. There are any number of variables between here and the end of the useful life of the reservoir.
I agree that it would appear to be inequitable to deduct from the net present value of the lost production an amount representing the present value of the deferred production. After all, the plaintiffs suffered the inconvenience and delay of 104 days lost production. In Continental Oil, the Court pointed out that even though the oil compa nies might ultimately produce from the reservoir all the oil that was economic to produce, they would nevertheless require 130 days longer to do so. In the final result, the Court assessed the plaintiffs' damages at the full value of the net production without any deduction for the present value of the oil that might ultimately be recovered.
I am strengthened in my conclusion that this is the appropriate method of assessment to be fol lowed in the case at bar by the decision of the U.S. Court of Appeals, Sixth Circuit, in National Steel Corp. v. Great Lakes Towing Co., supra. In that case, a steel company which owned a railroad bridge connecting its furnaces on an island in the river with its steel-making plant on the shore brought action against a towing company whose towed vessel collided with and damaged the bridge when a tow line snapped. The collision resulted in a loss to the steel company of fifty hours of production. The District Court entered judgment in favour of the plaintiff steel company for repair costs and expenses directly related to the interrup tion of production only. The claim for damages for lost production was denied on the ground that the plaintiff had failed to convince the Court that it had not made up the lost production. The Sixth Circuit Court of Appeals held that the plaintiff was entitled to recover for the lost production without regard to whether it had made up the lost
production. Peck J., delivering the judgment of the Court, said at page 343:
A few basic principles of tort liability must be kept in mind in order to understand the flaws in defendant's argument. First of all, a plaintiff is entitled to recover all damages proximately caused by the defendant which can be proved with a reasonable degree of certainty. When a defendant's negligence results in an interference with the use of plaintiffs property, the plaintiff is entitled to recover the value of the use during the interfer ence, or the value of the amount paid for a substitute. Restate ment of Torts, §§ 928, 931(a). The tort is complete and liability attaches when the harm is suffered. The plaintiff has a duty to take reasonable steps to mitigate damages, but this is a concept of avoidance, not repair. Thus the plaintiff must take all reasonable steps to prevent the accumulation of damages, and to minimize the effect of defendant's negligence; but the duty to mitigate applies only to damages which one can pre vent, not to damages already accrued. Finally, the principle which governs this lawsuit, a defendant cannot take advantage of events occurring after harm has occurred and liability has attached to reduce the damages for that harm.
The learned Judge continued in this vein at page 344:
Applying these principles to this case, the flaw in defendant's argument quickly becomes clear. The Towing Company's negli gence directly and immediately resulted in the loss of fifty hours of production. At the end of three days of production interruption, National Steel had a cause of action against the Towing Company for all losses suffered. Whatever occurred later, whether due to fortuitous events or plaintiffs diligence, cannot affect that liability.
This is not to say that the question of whether or not lost production was made up would never be relevant to a case of this sort; but when the only damages sought are for loss of use resulting in lost production, that question cannot affect the result.
Peck J. had earlier expressed the unequivocal view that the question whether the plaintiff could have made up the lost production was irrelevant and made no difference to the plaintiffs right to recov er damages for lost production. In the result, the Court reversed the decision of the District Court and remanded the cause for modification of its judgment in favour of the plaintiff to include the sum of $69,741, being the reasonable value of the production lost due to defendant's negligence.
Defendants' counsel endeavoured to distinguish the present case from the National Steel case by arguing that the profits in the latter were lost permanently, whereas in the former they were merely deferred. In my opinion, this argument is lacking in merit. Obviously, the Court in National Steel treated the question of whether the lost production was made up as being irrelevant to the plaintiffs claim for damages for loss of use based on the reasonable value of lost production.
The case of U. S. Oil of Louisiana, Ltd. v. Louisiana Power & Light Co., supra, was an appeal from a judgment at trial in a suit to recover against an electric utility for damages resulting from power outages and fires at a sulphur plant, wherein the trial Court found the value of produc tion lost to be $52,570. The defendant appealed the decision and the plaintiffs appealed the inadequacy of the damages award. On the dam ages appeal, the Court amended the trial judgment to reflect a loss of production in the amount of $121,943.50 attributable to one of the power out ages. Edwards J. said at page 912:
Defendants contend that plaintiffs suffered no loss of income for the sulfur not mined during the period between the outage and restoration of normal production because the sulfur was not lost but its production merely delayed. A similar contention was rejected in Continental Oil Company v. S.S. Electra, 431 F.2d 391 (5th Cir. 1970). The court therein noted that the plaintiff oil company suffered loss of production equal to net profit for oil the recovery of which was delayed while produc tion equipment was repaired. That reasoning is applicable herein. Stated simply, production for that period of time was forever lost.
In my view, the Bolivar case on which defen dants' counsel so strongly relies is distinguishable by the fact that there was no evidence that the plaintiff lost any sales, revenues or potential cus tomers as a result of the loss of use of its dredge for ten days or that its position had been worsened by the accident. If anything, it reaffirms the Con tinental Oil principle of damages recovery by emphasizing that proof of actual loss is necessary
to support a claim for damages for loss of use. Unlike Bolivar, there is ample evidence in the present case of loss of profits during the 104-day period of shut-down. As for the Norcen case, there is no explanation whatever of why the present value of lost production was deducted from the plaintiffs' damages award, nor of how that value was determined. I have been unable to find any reference to this aspect of the damages treatment in Norcen in any subsequent Canadian decisions. Plaintiffs' counsel urges that the present case is distinguishable from Norcen on the basis that there is no imminent likelihood of recovery of lost production. That may well be. In any event, I am not persuaded on the strength of the Norcen deci sion to subtract the present value of deferred production from the plaintiffs' claim for damages for loss of income attributable to lost production over the 104-day period, especially in face of the weight of more reasoned authority pointing the other way. In my opinion, the plaintiffs' losses accrued in a proximate sense when the liability attached for the harm done and the damages should be assessed accordingly, without having to inquire into subsequent events or happenings.
D. Quantification of Loss
I turn now to the actual calculation of the value of lost production according to the theory of loss presented by the plaintiffs' expert, Mr. Copeland, which I accept. I might point out that Mr. Cope- land was retained originally by Pembina's insur ance adjusters to quantify the loss of production during the indemnity period of 94 days, and his analysis of the loss sustained during the initial ten-day deductible period constitutes a separate calculation. Mr. Copeland estimated the lost pro duction during the 94-day period from January 3, 1984 to April 5, 1984 to be 225,254 mcf of natural gas. From this he deducted the amount of 23,518 mcf for the actual production during that period to arrive at a net lost production of 201,736 mcf. He then multiplied this amount by the unit price
figure of $3.54 to arrive at a sales value of lost production in the sum of $714,145. From this he deducted the sum of $240,166 for the expenses of petroleum gas revenue tax, royalties, overrides, and depletion at the rate of 8.05 per cent to arrive at a net claim figure of $473,979 from which he deducted the sum of $3,000 to account for several minor errors in his original calculations. This yielded a net sales value of lost production of $470,979, which he rounded off to $470,000.
The net value of lost production during the ten-day deductible period was calculated in like manner. However, Mr. Copeland did not make any deduction for depletion in his second calculation by reason that he treated depletion in the account ing context of something to be deducted from revenue received. As he explained it, the gas vented and lost to the atmosphere during the ten- day deductible period represented gas that was completely lost for which no revenue would ever be received, and so there should be no deduction for depletion. I consider this to be a reasonable expla nation in the circumstances. The end result of Mr. Copeland's calculations was a net loss figure of $102,226 for the ten-day deductible period, which I accept.
Counsel for the plaintiffs submits that this net loss figure should be increased by 25 per cent to reflect an additional quantity of gas lost to the atmosphere during the ten-day period. He bases this on the evidence of the plaintiffs' superintend ent, Mr. Simpson, who testified that lowered back pressure caused by the venting to the atmosphere would have resulted in an increased flow of gas, which he estimated at this percentage. Under cross-examination, Mr. Simpson conceded that the figure was not firm and could lie anywhere be tween zero and 30 per cent, and that 25 per cent was merely his best estimate. I agree with counsel for the defendants that this number "was just picked out of the air" and had no basis in reality or experience, and ought not to be taken into account. Adding the figure of $102,226 to the net sales
value of $470,000, gives a net total value of lost production for the period from December 24, 1983 to April 5, 1984 of $572,226, which I assess as the plaintiffs' general damages for loss of business income.
To recapitulate for the sake of convenience, the plaintiffs' damages are assessed as follows (round- ed version):
Cost of temporary repairs $186,956
Cost of permanent repairs $114,618
Loss of business income $572,226
TOTAL $873,800
In the result, the plaintiffs are entitled to recover from the defendants total damages in the sum of $873,800.
IV. Interest
The final question is whether pre-judgment in terest should be awarded as an integral part of the plaintiffs' damages and, if so, from what date it should run. Counsel are agreed that the applicable rate of interest would be 9.5 per cent.
Counsel for the defendants submits, firstly, that I should exercise my discretion against allowing any pre-judgment interest in the present case, given the novelty of the various issues raised there in and, particularly, the lack of jurisprudence bearing on these issues and the assessment of damages for business interruption loss. He cites Nissan Automobile Co. (Canada) Ltd. v. The Continental Shipper, [1974] 1 F.C. 88 (T.D.), wherein Urie J., on a Rule 324 [Federal Court Rules, SOR/71-68] application to reconsider judg ment, confirmed that interest was disallowed pur posely because of the reasonableness of the defence and the lack of prior jurisprudence. Secondly, defendants' counsel submits that the time for cal culation of any pre-judgment interest should run only from December 20, 1984, the date when the plaintiffs first gave notice of the damaged pipeline and their estimated losses resulting therefrom. In his submission it would be unfair to award pre judgment interest prior to that date, since the
defendants knew nothing of the damaged pipeline nor the plaintiffs' claim in respect thereof. Thirdly, it is submitted that the estimated cost of perma nent repairs in the sum of $114,618 should be excluded from any award of pre-judgment interest because the repairs were never executed and the plaintiffs were not out-of-pocket for that amount.
Counsel for the plaintiffs points out that the prayer for relief in the statement of claim claims interest "from the date of the loss until the date of Judgment". He also points to the invariable prac tice in admiralty cases of allowing pre-judgment interest as an integral part of the damages award ed and submits that the exercise of judicial discre tion with respect thereto must be related to the task of fully compensating the plaintiff or the money wrongfully withheld, citing John Maryon International Limited et al. v. New Brunswick Telephone Co., Ltd. (1982), 43 N.B.R. (2d) 469; 141 D.L.R. (3d) 193; 113 A.P.R. 469; 24 CCLT 146 (C.A.); and Irvington Holdings Ltd. v. Black et al. and two other actions (1987), 58 O.R. (2d) 449 (C.A.), at page 484. As for the point that pre-judgment interest should be calculated only from the date of notification of the claim, plain tiffs' counsel submits that the lengthy period for investigating the cause of damage to the pipeline and identifying the responsible culprit was not unreasonable in the circumstances.
In admiralty cases, interest is normally awarded as an integral part of the damages suffered by the plaintiff from the time of the injury or loss, and the discretion for awarding pre-judgment interest should be refused only in exceptional cases: see Canadian General Electric Co. Ltd. v. Pickford & Black Ltd., [1972] S.C.R. 52; (1971), 20 D.L.R. (3d) 432; Bell Telephone Co. v. The Mar- Tirenno, [1974] 1 F.C. 294; 52 D.L.R. (3d) 702 (T.D.); affd [1976] 1 F.C. 539; 71 D.L.R. (3d) 608
(C.A.); Davie Shipbuilding Limited v. The Queen, [1984] 1 F.C. 461; 4 D.L.R. (4th) 546; 53 N.R. 50 (C.A.); and Drew Brown Ltd. v. The "Orient Trader", [1974] S.C.R. 1286.
In Canadian General Electric Co. Ltd. v. Pick- ford & Black Ltd., supra, the Supreme Court held that the plaintiff was entitled to interest on its claim for cargo damage from the date when the goods should have been delivered. Ritchie J. allud ed to the principles administered in admiralty courts with respect to the allowance of pre-judg ment interest, and stated at page 57:
It is thus well settled that there is a clear distinction between the rule in force in the common law courts and that in force in admiralty with respect to allowing a claim for interest as an integral part of the damages awarded.
In Bell Telephone Co. v. The Mar- Tirenno, supra, Addy J., at trial, stated the following prin ciple at pages 311-312:
It is clear that this Court, under its admiralty jurisdiction, has the right to award interest as an integral part of the damages suffered by the plaintiff regardless of whether the damages arose ex contractu or ex delicto.
... interest in these cases is not awarded to the plaintiff as punitive damages against the defendant but as part and parcel of that portion for which the defendant is responsible of the initial damage suffered by the harmed party and it constitutes a full application of the principle of restitutio in integrum.
This principle was expressly approved by Mr. Jus tice Urie in delivering the judgment of the Federal Court of Appeal in the Davie Shipbuilding case, supra.
In Drew Brown Ltd. v. The "Orient Trader", supra, the owners of a cargo of tin brought action against the carrier for cargo damage and the latter counterclaimed for contribution in accordance with the general average terms of the contract. The Trial Judge dismissed the claim of the owners and allowed the counterclaim for general average adjustment, but disallowed interest to the date of judgment on the general average adjustment awarded against the owners, and this became the subject-matter of a cross-appeal by the carrier. A majority of the Supreme Court dismissed the
appeal of the owners and allowed the carrier's cross-appeal, Hall and Spence JJ. dissenting.
Laskin J., dealing with the Trial Judge's reasons on the counterclaim award, said at page 1335:
I see nothing in the trial judge's reasons to support his refusal to allow interest to the date of judgment. The delay in asserting the counterclaim, in which interest was claimed on the general average contribution, is not a mitigating factor in favour of the appellant when it had from the outset resisted the demand for such contribution. Moreover, the complexity of the issues with which the trial judge had to deal affected both parties equally. In line with the principle considered by this Court in Canadian General Electric Co. Ltd. v. Pickford and Black Ltd., the respondent should have interest from the date of the general average adjustment to the date of judgment. There are no special considerations to support a discretionary exercise of authority to deny interest for this period.
I find therefore that the plaintiffs are entitled to pre-judgment interest on the total damages award of $873,800 from the date of injury on December 24, 1983 to the date of judgment at the agreed rate of 9.5 per cent per annum. Moreover, to para phrase the words of Laskin J. in the Orient Trader case, I am clearly of the opinion that there are "no special considerations to support a discretionary exercise of authority to deny interest for this period".
V. Conclusion
For the foregoing reasons, I award judgment in favour of the plaintiffs for total damages of $873,800, together with pre-judgment interest thereon at the rate of 9.5 per cent per annum from December 24, 1983 to the date of judgment and post-judgment interest thereafter at the same rate, until payment. The plaintiffs are entitled to their taxable costs of the action.
 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.